Sec. 78-123. - Facility servitudes over city-owned property; fees and payments.
(a) Facility servitude for use of city-owned property. No person shall locate or construct a facility across, in, over, or under city-owned property, excluding the city's public rights-of-way, without first having obtained a facility servitude authorized by resolution of the city council and executed by the mayor, or his/her designee. The city engineer is authorized to establish a policy and regulations for the issuance of such facility servitudes. (b) Fees. (1) Facility servitude application processing fee. The facility servitude application processing fee for persons or entities using city-owned property shall be $1,500.00. (2) Facility servitude fee for use of city-owned property. When a facility servitude is granted across, in, over, or under city-owned property pursuant to this section, the servitude fee shall be an amount no less than the appraised value of the servitude for 20 years as determined by an appraiser with an MAI designation (Member of the Appraisal Institute) or an appraiser approved by the city engineer or his/her designee. The MAI appraiser or city engineer approved appraiser shall be retained by the prospective servitude owner. Full payment for the initial 20-year servitude shall be made prior to granting a permit authorizing use of the servitude. (c) Payments. (1) Renewal of the servitude. The servitude may be extended and renewed in 20-year increments by the servitude owner. The servitude owner shall within 180 days prior to the end of the initial 20-year servitude period, notify the department of engineering and environmental services by certified mail that an extension/renewal is requested. The servitude owner shall obtain a new appraisal by an appraiser with an MAI designation (Member of the Appraisal Institute) or an appraiser approved by the city engineer or his/her designee. Full payment of an amount equal to the new appraisal shall be made to the city prior to the beginning of the renewal of any new 20-year period. (2) Late payments. After the initial 20-year period, in the event full payment is not made to the city prior to the beginning of any subsequent 20-year period, the city shall give the servitude owner written notice of failure to make payment and the servitude owner shall have 60 days from receipt of said notice to complete a new appraisal and provide payment to the city without late penalties being applied. The absence of a city issued failure to make payment notice does not release the servitude owner from its obligation to pay city. (3) Penalty for late payments. If the servitude owner does not remit the servitude fee within 60 days of receipt of a written failure to make payment notice the servitude owner shall be assessed a late penalty on the 61st day of 20 percent of the servitude renewal annual fee. This provision shall preempt any other city ordinance, regulation, or order regulating late payment of fees. (4) Termination for non-payment. In the event payment is not made within the 60-day failure to make payment notice period, the city shall issue the servitude owner a notice of termination. Said notice of termination shall advise the permittee that all fees, including any late payment penalties, are currently due and if full payment is not received within 90 days of receipt of the notice of termination the servitude shall terminate.
(Ord. No. 56, 2018, 7-24-18; Ord. No. 190, 2019, 1-14-20)