§ 53-14 — Permit requirements – Time for completing work
Baltimore City Code (current through Ord. 26-129 (July 17, 2026); publication of Oct. 18, 2026) · Baltimore City Code, Article 7, § 53-14
Corpus is an independent public-information project, not the official City of Baltimore website. Stable reference: corpuslaw.us/code/6514a076-e3c4-4e5c-a840-b0fd9b063b34
§ 53-14. Permit requirements – Time for completing work.
All work covered by a permit issued under this subtitle shall be completed within 30 days from the date shown on the permit.
(Ord. 15-435; Ord. 76-139; Ord. 46-396; Ord. 12-154.)
Ask a question about Baltimore law
Corpus searches the Baltimore sections it holds and shows the ones that match, with their citations. Free, no sign-in.