Sec. 17-40. - Contract modifications; change orders; price adjustments.
(a) The following contract changes (including contract modifications, change orders, and price adjustment) must be approved by the Council: (1) Changes to any contract not originally awarded by the Council when the cumulative value of the original contract and all changes to the contract exceed two hundred fifty thousand dollars ($250,000.00); (2) Changes to any contract originally awarded by the Council when the cumulative value of all changes exceeds the greater of: a. Two hundred fifty thousand dollars ($250,000.00), or b. Ten (10) percent of the original contract. (3) Changes to any contract modified by Council where the cumulative value of all changes exceeds the greater of: a. Two hundred fifty thousand dollars ($250,000.00), or b. Ten (10) percent of the modified contract. (b) Changes to any contract, including contract modifications, change orders, and price adjustments must be approved in accordance with the original contract, in writing, by the City Manager or designee, when the cumulative value of the original contract and all changes to the contract exceed fifty thousand dollars ($50,000.00).
(Ord. No. 13-02, 6-10-02; Ord. No. 29-04, 10-4-04; Ord. No. 4-18, 2-5-18; Ord. No. 14-24, 9-16-24)