Sec. 10-116. Enforcement.
In the event that there are violations of the blasting plan, blasting submittal, or blasting permit, or any other violation of this article, a stop work order may be issued on all construction or development related to the permitted operation. The permittee shall then be required to submit a revised blasting plan to the AHJ for review and approval. Work shall not be allowed to continue until the revised blasting plan is approved.
(Ord. No. 131-24/25, 2-24-25)