§ 17-263 — Permit required; application information; permit process; provider and city responsibilities; time periods; tolling; deemed approved; basis for denial; resubmittal; application fees; micro wireless facility exemption; alternate siting; decommissioning sites
Code of Ordinances of the City of Dearborn, Michigan (2026 S-07: Code and Zoning updated through September 22, 2026) · Dearborn City Code § 17-263
Corpus is an independent public-information project, not the official City of Dearborn website. Stable reference: corpuslaw.us/code/84a5f06a-3f04-49dd-9743-ebf0c579d015
Sec. 17-263. Permit required; application information; permit process; provider and city responsibilities; time periods; tolling; deemed approved; basis for denial; resubmittal; application fees; micro wireless facility exemption; alternate siting; decommissioning sites.
(a) This section applies to activities of a wireless provider within the public right-of-way. (b) In-kind contributions to the city are not permitted in lieu of rates and fees described in this article. (c) Permit required. Except as otherwise provided in the Act and this article, a wireless provider may not co-locate a small cell wireless facility or install, modify, or replace a utility pole, city pole, or wireless support structure on which a small cell wireless facility will be co-located within the ROW without first applying for and receiving a permit from the city in a form and subject to such terms and conditions as are acceptable to the city. (d) Application. A wireless provider shall apply for a permit by filing a written application with the Department of Economic Development on a form furnished by the department. The applicant shall provide all the information and documentation required by the city to enable it to make an informed decision with regard to its criteria for authorizing ROW accessing. Applications shall be complete and include all required information. An application is not considered complete until all required materials have been submitted and accepted by the city. At a minimum, the applications shall include the following: (1) Applicant contact information, including address, phone contact, 24-hour emergency contact information, email address, and any applicable license numbers; (2) Applicant’s contractor and subcontractor information, including the names, addresses, phone contact, email addresses, emergency contact numbers, and name of the supervisor(s) assigned to any facility project of all contractors and subcontractors that will work within the city’s ROW under a permit; (3) Number of wireless facilities that will be deployed; (4) The scope of the deployment, including whether the deployment is modification of a current facility, utility pole, or city pole; co-location on an existing utility pole, city pole, or wireless support structure; or installation of a new or replacement wireless support structure or utility pole; (5) GIS maps and coordinates detailing locations for each proposed small cell wireless facility and related facilities associated with each facility; (6) Site plan at a scale not smaller than one-inch equals 20 feet with dimensions showing the following: a. Proposed location, including nearest cross street intersection; b. Height of the proposed facility; c. The distance of the proposed facilities and the nearest property line, roadways, rights-of-way, driveways, curb cuts, crosswalks, and utilities within the rights-of-way; and d. Any other proposed improvements that are part of the deployment. (7) An application fee as established pursuant to this article; (8) Executed permit and consent agreement for access to and use of the ROW located in the city, if applicable; (9) Specification sheets for all attachments and equipment that will be located within the city, including the dimensional size of the small cell wireless facility and all other wireless equipment; (10) Attachment drawings and demonstrations of each type of installation, including photograph simulations showing co-locations, new or replacement utility poles, wireless support structures, and concealment and design characteristics satisfying this article; (11) Pole loading analysis if being co-located on a utility pole or city pole located in a ROW in the city or wireless support structure; (12) A certificate of compliance with FCC rules related to radio frequency emissions from a small cell wireless facility; (13) Proof of notification to every other affected authority and all necessary permits, permit applications, or easements to ensure all necessary permissions for the proposed activity are obtained; (14) An attestation that the small cell wireless facilities will be operational for use by a wireless services provider within one year after the permit issuance date. Failure to abide by this term shall result in termination of any permit issued in reliance on such attestation. (15) Work plan describing the location of the proposed work, the work to be performed, the limits of disturbance to the ROW and the method and materials to be used; (16) Landscape plans for ground-mounted facilities, if applicable; (17) Site/structure remediation plans for restoring any public property after removal of the wireless facilities, if applicable; (18) To the extent available, identify other known permits related to the deployment, including any applicable METRO Act (PA 48 of 2002, MCL 484.3101, et seq.) application and permit, related to the small cell wireless facility, and any permits required by the state, county, Michigan Department of Transportation, or other right-of-way, private property, or wireless support structure owner; (19) For deployments in residential or non-residential districts, documentation of compliance with design and location requirements where applicable; (20) For deployments in the ROW, documentation showing adequate insurance as required by this article; (21) Proof of a performance bond meeting the requirements of this article; (22) Any additional information requested by the city. (23) Upon receipt of an application, the Department of Economic Development shall forward the application and all accompanying materials, documents, and information to the Department of Public Works and Facilities for review pursuant to subsection (h) below. (e) Confidential information. If a wireless provider claims that any portion of the information submitted by it as part of its application contains trade secret, proprietary, or confidential information, which is exempt from the Freedom of Information Act (MCL 15.231, et seq.), the wireless provider shall prominently so indicate on the application and on the confidential documents. (f) Consolidated application. An applicant may file a consolidated application and receive a single permit for the co-location of up to 20 small cell wireless facilities. The small cell wireless facilities within a consolidated application must consist of substantially similar equipment and be placed on similar types of utility poles or wireless support structures. The city may approve a permit for one or more small cell wireless facilities included in a consolidated application and deny a permit for the remaining small cell facilities. (g) Application fee. Except as otherwise provided by the Act, the application fee for a permit under this subsection shall be: (1) $200.00 for each small cell wireless facility alone. (2) $300.00 for each small cell wireless facility and a new utility pole to which it will be attached. (3) Every 5 years after the effective date of the Act (March 12, 2019) the application fee authorized in this subsection shall be increased by 10% and rounded to the nearest dollar. (h) Permit approval process and timeline. Permit applications shall comply with the following process: (1) Initial review for completeness. Within 25 days after receiving an initial application, the city shall notify the applicant in writing whether the application is complete. If incomplete, the notice will delineate all missing documents or information. The notice tolls the running of the time for approving or denying an application from the time notice is provided to the time the city receives a supplemental submission. (2) Supplemental submissions. If the applicant makes a supplemental submission in response to the notice of incompleteness, the city will so notify the applicant in writing within 10 days, delineating the previously requested and missing documents or information. The time period for approval or denial is tolled in the case of second or subsequent notices under the procedures identified in preceding subsection (h)(1). (3) Notice of approval or denial. The city shall approve or deny the application and notify the applicant in writing within the following period of time after the complete application is received: a. Co-location time period. For an application for the colocation of small cell wireless facilities on a utility pole, 60 days, subject to the following adjustments: 1. Add 15 days if an application from another wireless provider was received within one week of the application in question. 2. Add 15 days if a timely extension was requested. b. New or replacement forty-foot (40') pole and limited equipment. For an application for a new or replacement utility pole that meets the height requirements of Sec. 17-262 and associated small cell facility, 90 days subject to the following adjustments: 1. Add 15 days if an application from another wireless provider was received within one week of the application in question. 2. Add 15 days if a timely extension is requested. (4) Deemed approved. If the city fails to comply with this subsection, an application that is otherwise complete is considered to be approved subject to the condition that the applicant provide the city with not less than 7 days’ advance written notice that the applicant will be proceeding with the work pursuant to this automatic approval and the applicant shall be responsible to comply with all provisions of this section and the Act. Such advance notice must be provided in writing. (5) Basis for denial. The city may deny a completed application for a proposed collocation of a small cell wireless facility or installation, modification, or replacement of a utility pole that meets the height requirements in Sec. 17-262 if the proposed activity would do the following: a. Materially interfere with the safe operation of traffic control equipment. b. Materially interfere with sight lines or clear zones for transportation or pedestrians. c. Materially interfere with compliance with the Americans with Disabilities Act of 1990, Public Law 101-336, or similar federal, state, or local standards regarding pedestrian access or movement. d. Materially interfere with maintenance or full unobstructed use of public utility infrastructure under the jurisdiction of an authority. e. With respect to drainage infrastructure under the jurisdiction of the city, either of the following: 1. Materially interfere with maintenance or full unobstructed use of the drainage infrastructure as it was originally designed; or 2. Not be located a reasonable distance from the drainage infrastructure to ensure maintenance under the drain code of 1956, PA 40 of 1956, MCL 280.1 to 280.630, and access to the drainage infrastructure. f. Fail to comply with reasonable, nondiscriminatory, written spacing requirements of general applicability adopted by ordinance or otherwise that apply to the location of groundmounted equipment and new utility poles and that do not prevent a wireless provider from serving any location. g. Fail to comply with applicable codes and zoning regulations. h. Fail to comply with any provision of this article. i. Fail to meet reasonable, objective, written stealth or concealment criteria for small cell wireless facilities applicable in a historic district or other designated area, as specified In an ordinance or otherwise and applied in a nondiscriminatory manner applicable to all other occupants of the ROW, including electrical utilities, incumbent or competitive local exchange carriers, fiber providers, cable television operators, and the city. (6) Reasons for denial; resubmission and 30-day time period. If the completed application is denied under this section, notice of the denial shall be provided to the applicant and shall explain the reasons for the denial and, if applicable, cite the specific provisions of applicable codes on which the denial is based. The applicant may cure the deficiencies identified by the city and resubmit the application within 30 days after the denial without paying an additional application fee. The city shall approve or deny the revised application within 30 days, and shall limit its review of the revised application to the deficiencies cited in the denial. (7) Approval of an application authorizes the wireless provider to undertake the installation, collocation, and maintenance of such facilities. (8) The city shall not institute a moratorium on filing, receiving, or processing applications or issuing permits for the collocation of small cell wireless facilities or the installation, modification, or replacement of utility poles on which small cell wireless facilities will be co-located. (9) Extension of time. The city and an applicant may extend a time period under this subsection by mutual agreement. (i) Operational timeline; void for lack of progress. Within one year after a permit is granted, a wireless provider shall complete co-location of a small cell wireless facility that is to be operational for use by a wireless services provider, unless the city and the applicant agree to extend this period or the delay is caused by the lack of commercial power or communications facilities at the site. If the wireless provider fails to complete the colocation within the applicable time, the permit is void, and the wireless provider may reapply for a pennit (j) Revocation of permit. The city may revoke a permit, upon 30 days’ notice and an opportunity to cure, if the permitted small cell wireless facilities and any associated utility pole fall to meet the requirements of this article. (k) Permit exception. The city shall not require a permit or any other approval or require fees or rates for the following: (1) Replacement of a small cell wireless facility with a small cell wireless facility that is not larger or heavier, as long as such replacement is in compliance with this article and all applicable code requirements. (2) Routine maintenance of a small cell wireless facility, utility pole, or wireless support structure. (3) The installation, placement, maintenance, operation, or replacement of a micro wireless facility that is suspended on cables strung between utility poles or wireless support structures in compliance with this article and all applicable code requirements. (l) Alternate siting. Upon receipt of an application to place a new utility pole, the city may propose and the applicant shall use an alternate location within the ROW or on properly or structures owned or controlled by the city within 75 feet of the applicant’s proposed location if reasonably achievable. (m) Decommissioning sites. A wireless provider shall notify the city in writing before discontinuing use of a small cell wireless facility, utility pole, or wireless support structure. The notice shall specify when and how the wireless provider intends to remove the small cell wireless facility, utility pole, or wireless support structure. The wireless provider shall return the property to its pre-installation condition. If the wireless provider does not complete removal within 45-days after the discontinuance of use, the city may complete the removal and assess the costs of removal against the wireless provider. A permit under this section for a small cell wireless facility expires upon removal of the small cell wireless facility. (n) A provider shall obtain a permit for any work that will affect traffic patterns or obstruct vehicular or pedestrian traffic in the ROW. (Ord. No. 22-1749, 6-7-22)