Sec. 3-455. - Procedures for construction contracts.

(a) The following shall apply to construction contracts in which the estimated cost thereof is more than $400,000.00: (1) Bid submissions. Bidders shall submit an affidavit of intended utilization with their bids. (2) Forty-eight-hour submissions. Bidders on city contracts shall submit the following within 48 hours after bid opening: a. A contractor utilization plan in conformance with section 3-433 hereof; and b. Confirmation of subcontractor participation or letters of intent to subcontract; and c. Good faith efforts documentation pursuant to sections 3-437 and 3-441 if the bidder failed to meet or exceed the goals. (3) Timely submission of the contractor utilization plan is a material element of the submission. The director is authorized to extend the forty-eight-hour deadline for confirmation of participation or letters of intent to subcontract but not the deadline for submission of the contractor utilization plan. (4) The apparent successful bidder shall submit documentation of good faith efforts made prior to 48 hours after bid opening when requested by the city or the incentive agency. (5) A notarized affidavit certifying actual SBE participation in the contract, including the names of such SBEs and the participation amount, and a certification that all SBE subcontractors and other subcontractors have been paid must be submitted by the contractor prior to the city's release of retainage under the contract. Partial release of retainage for subcontractors whose work is completed may be approved with the submission of a notarized affidavit certifying that their work under the contract is complete. (6) Any increase in the amount of SBE participation after submission of the contractor utilization plan shall not count toward meeting the contract goals, unless otherwise permitted under section 3-443 hereof. (7) Bid shopping is prohibited.

(Ord. No. 260692, § 1, 8-13-26)