§ 88-545-09 — LAPSE OF APPROVAL
Code of Ordinances of Kansas City, Missouri (Supp. No. 140, Update 1: codified through Ordinance No. 260692, enacted August 13, 2026) · Kansas City Zoning and Development Code § 88-545-09
Corpus is an independent public-information project, not the official City of Kansas City website. Stable reference: corpuslaw.us/code/a2e38708-ba27-4c03-909c-ae22f2e28b09
88-545-09 - LAPSE OF APPROVAL
Once a preliminary plat is approved, applicants have 2 years from the date of approval to submit a final subdivision plat for the subdivision or for an approved phase of the subdivision. If a final plat is not submitted within the required 2-year period, the preliminary plat approval will lapse and be of no further effect. The city plan commission is authorized to grant a one-time extension of the 2-year period, for not to exceed one year. This extension may be granted only if the applicant requests the extension before the approval lapses.
Ask a question about Kansas City law
Corpus searches the Kansas City sections it holds and shows the ones that match, with their citations. Free, no sign-in.