Sec. 96-44. - When permit is required.
A land disturbance permit is required for all land disturbance activity that disturbs one acre or greater, or that disturbs less than one acre when part of a larger common plan of development or sale that will disturb a cumulative total of one or more acres over the life of the project. Nothing shall prevent the department from taking action, including the requirement for issuance of any permits under this article, if any of the operations exempted under section 96-45 should cause pollution of the MS4 or waters of the state or otherwise violate this article. The responsible party shall obtain a land disturbance permit from the department prior to commencing land disturbance activity. Demolition that involves land disturbance is considered the first phase of construction for sites disturbing one acre or greater, and the land disturbance permit shall be issued prior to issuance of associated demolition permits, unless an exception is granted by the director.
(G.O. No. 6445, § 1, 4-9-2018; G.O. No. 6671, § 1, 7-26-2021)
Ask a question about Springfield law
Corpus searches the Springfield sections it holds and shows the ones that match, with their citations. Free, no sign-in.