§ 605 — DESIGN REQUIREMENTS
Comprehensive Development Regulations for the City of Flowood; partial · Flowood Development Regulations § 605
Corpus is an independent public-information project, not the official City of Flowood website. Stable reference: corpuslaw.us/code/1163e64f-ec3d-44cf-bba0-cbc5c4dd96bf
SECTION 605 DESIGN REQUIREMENTS
605.1 Grading erosion control practices, sediment control practices, and waterway crossings shall meet the design criteria set forth in the most recent version of City of Flowood’s Erosion and Sediment Control/Grading Ordinance, the requirements of MDEQ, and shall be adequate to prevent transportation of sediment from the site to the satisfaction of City of Flowood.
605.2 Clearing and Grading
a. Clearing and grading of natural resources, such as forest and wetlands, shall not be permitted, except when in compliance with all other chapters of these regulations.
b. Clearing techniques that retain natural vegetation and retain natural drainage patterns, as described in the MDEQ Design Manual, shall be used to the satisfaction of the City of Flowood.
c. Phasing of construction activities shall be required on all sites disturbing greater than thirty (30) acres, with the size of each phase to be established during plan review and as approved by City of Flowood.
d. Clearing (including logging operations), except that necessary to establish sediment control devices, shall not begin until all sediment control devices have been installed and have been stabilized.
e. Cut and fill slopes shall be no greater than 3:1, except as approved by City of Flowood to meet other community or environmental objectives.
f. At a minimum, all silt fences shall be installed using metal T-posts at 6’ spacing. No silt fences may be installed using wood posts.
g. See City standard details for details on installation requirements for certain erosion control BMP’s.
605.3 Erosion Control
a. Soil must be permanently stabilized within seven (7) days of clearing or inactivity in construction.
b. If vegetative erosion control methods, such as seeding, have not become established within two (2) weeks, the City of Flowood may require that the site be reseeded, or that a non-vegetative option be employed.
c. On steep slopes or in drainage ways, special techniques such as hydroseeding or erosion control blankets that meet the design criteria outlined in the MDEQ Design Manual shall be used to ensure stabilization.
d. Soil stockpiles must be stabilized with sediment barriers or covered at the end of each workday.
e. Whenever construction is planned to be inactive for 30 days or more, the entire site must be stabilized, using heavy mulch layer, or another method that does not require germination to control erosion.
f. Techniques such as chemical erosion control shall be employed to prevent the blowing of dust or sediment from the site.
g. Techniques that divert upland runoff past disturbed slopes shall be employed.
605.4 Sediment Controls
a. Sediment controls, per MDEQ requirements, shall be provided in the form of settling basins or sediment traps or tanks, and perimeter controls.
b. Where possible, settling basins shall be designed in a manner that allows adaptation to provide long-term stormwater management.
c. Adjacent properties shall be protected using a temporary vegetated buffer strip, in combination with perimeter controls. Refer to the MDEQ Design Manual for recommended width and plant categories.
605.5 Waterways and Watercourses
a. When a wet watercourse must be crossed regularly during construction, a temporary stream crossing shall be provided, and an approval obtained from the appropriate governmental agency. A temporary stream crossing can be a low water crossing, a culvert crossing, or a bridge with or without embankment approaches.
b. When in-channel work is conducted, the channel shall be stabilized before, during and after work.
c. Areas where erosion, scouring or the loss of materials in a ditch or channel is likely over time (such as bends, steeply sloped sections, etc.) shall be protected from by riprap, turf reinforcement matting, paving, or some other City approved measure.
d. All on-site storm water conveyance channels shall be designed according to the criteria outlined in the MDEQ Design Manual.
e. Stabilization adequate to prevent erosion must be provided at the outlets of all pipes and paved channels.
605.6 Construction Site Access
a. A temporary access road shall be provided at all sites. The construction access road meeting the requirements of the MDEQ Design Manual shall be provided to the site at all times during construction.
b. Other measures may be required at the discretion of the City of Flowood to ensure that sediment is not tracked onto public streets by construction vehicles or washed into storm drains.
c. It shall be the responsibility of the developer to ensure that construction siltation is cleaned from the public road access at the end of each workday. If the developer or his contractor does not maintain a clean access drive, he shall be issued a stop work order until such clean-up is complete.