Sec. 23-106. - Construction timing.
The applicant or his/her contractors may not proceed with any construction work on a proposed subdivision, including grading and excavation relating to public improvements, until the governing body has given preliminary plat approval of the proposed subdivision plat. If improvements are initiated prior to final plat approval, the subdivider shall assume all risks and liability for error in improvement placement and the improvements must comply with the conditions and agreements of the preliminary plat approval.
(Ord. No. 06-5359, § 2, 2-13-06; Ord. No. 26-5931, § 1, 5-26-26)
Ask a question about Billings law
Corpus searches the Billings sections it holds and shows the ones that match, with their citations. Free, no sign-in.