§ 10.04.110 — Failure to complete demolition; work performed by city; costs

Bozeman Municipal Code, City of Bozeman, Montana (Codified through Order No. 2026-11, adopted September 15, 2026. (Supp. No. 16, Update 1)) · Bozeman Municipal Code § 10.04.110

Corpus is an independent public-information project, not the official City of Bozeman website. Stable reference: corpuslaw.us/code/d76e36c7-6c0c-46b1-802d-01e3fb4c52f4

Sec. 10.04.110. - Failure to complete demolition; work performed by city; costs.

If the permittee fails or refuses to complete the demolition authorized by this article within a reasonable period of time, and, after ten days' written notice having been given to the permittee and owner, the city may proceed to have the necessary work completed and may recover the expense of such work from the surety bond required to be posted by section 10.04.090. The permittee shall be liable for any amounts not covered by the surety bond.

(Code 1982, § 15.28.120; Ord. No. 1631, § 27(15.28.120), 4-4-2005)

Ask a question about Bozeman law

Corpus searches the Bozeman sections it holds and shows the ones that match, with their citations. Free, no sign-in.