Sec. 18-58. - Contract pre-award compliance procedures.
(a) In all solicitations for which contract specific goals have been established, the bidder shall submit a participation plan in accordance with the policy and the schedule and instructions required by the city manager. If the bidder that is recommended for contract award fails to achieve the contract specific goals, documentation of its good faith efforts to do so is due at the time specified in the solicitation. (b) Any agreement between a bidder and a UBE in which the bidder requires that the UBE not provide subcontracting quotations to other bidders is prohibited. (c) Where the bidder has not achieved the contract specific goals, the city manager will follow guidelines in the city's policy to determine whether the bidder has made good faith efforts to achieve those goals. (d) In determining whether a bidder has made good faith efforts, the performance of other bidders in meeting the contract specific goals may be considered. (e) A signed letter of intent from all listed UBEs describing the work, including goods and services to be performed or provided by the UBE and the agreed upon dollar value for bids or percentage of professional services pursuant to a request for proposals or description of the services to be rendered pursuant to a request for qualifications, shall be due in accordance with the city manager's instructions. (f) The city manager or designee shall review the participation plan prior to award, including the scope of work and the letters of intent from UBEs. The city manager may request clarification in writing of items listed in the participation plan, provided such clarification shall not include the opportunity to augment listed UBE participation or good faith efforts. (g) If the city manager determines that the participation plan demonstrates that the contract specific goals have been achieved or good faith efforts were made, or that award is in the best interest of the city, then the city manager shall recommend award. (h) If the city manager finds that a bidder did not make good faith efforts, the city manager shall send notice of the finding to the bidder using the procedure outlined in Section 18-63.
(Ord. No. 16292, § 1, 4-1-2024)
Ask a question about Durham law
Corpus searches the Durham sections it holds and shows the ones that match, with their citations. Free, no sign-in.