§ 62-155 — Restoration of right-of-way before issuance of certificate of compliance
Code of Ordinances, City of Durham, North Carolina (Supp. No. 37, Update 1: codified through Ordinance No. 16682, adopted June 15, 2026) · Durham City Code § 62-155
Corpus is an independent public-information project, not the official City of Durham website. Stable reference: corpuslaw.us/code/ff73bbf7-72fe-4eff-952e-eace1926c475
Sec. 62-155. - Restoration of right-of-way before issuance of certificate of compliance.
(a) No certificate of compliance shall be issued for any building construction prior to certification by the city engineer or his or her designee that the condition of the street and street right-of-way adjacent to the building site is acceptable. The inspection shall include: (1) Proper restoration of grade; (2) Proper construction or repair of curbs, gutters and sidewalks; (3) Proper installation of gutter downspout and/or yard drains; (4) Proper installation and adjustment of sewer lateral cleanouts, water meters and meter boxes; (5) Proper location and construction of driveway turnouts and/or driveway pipes; (6) Proper restoration of drainage ditches; (7) Proper permanent erosion control installations, including seeding and mulching of all disturbed areas; (8) Proper restoration of street paving (including repair of damage by construction equipment); (9) Proper restoration or repair of street plantings; (10) Proper construction of on-site storm drainage facilities. (b) Compliance with the above requirements concerning restoration shall not prohibit the city from inspecting other damage to the street and street right-of-way and from ensuring compliance with other applicable city ordinances.
(Code 1982, § 18-87; Ord. No. 8013, § 3, 2-19-1990)
Ask a question about Durham law
Corpus searches the Durham sections it holds and shows the ones that match, with their citations. Free, no sign-in.