24.38.040 On-site Wastewater Treatment Systems; Construction Permit; Alteration Permit.
No person shall construct a new on-site wastewater treatment system or cause the same to be done without an on-site wastewater treatment system construction permit issued by the Health Director. No person shall resize or alter the dike of a lagoon, replace tanks, soil absorption, infiltrative or evaporative systems, or extend the laterals to an existing system or cause the same to be done without an on-site wastewater treatment system alteration permit issued by the Health Director. An alteration permit shall not be required for a repair as defined in this chapter. (a) Application for a permit to construct or alter an on-site wastewater treatment system shall be submitted to the Health Director on forms furnished by the Health Director and shall include information as required by Section 4 of the design standards, information specified in the application form, and any other necessary information to determine whether the construction, alteration, or extension will conform to the provisions of this chapter and the design standards adopted pursuant to this chapter. The application shall include evidence to demonstrate to the satisfaction of the Health Director that there is no community sewer (wastewater works) or other part of the community sewage system within 300 feet of such building or premises into which the sewage can be discharged. (b) When, upon review of the application, the Health Director determines that the proposed design meets the requirements of this chapter and all applicable fees have been paid, a written construction or alteration permit shall be issued. (c) The on-site wastewater treatment system must be constructed according to the Health Director approved design. (d) When, upon review of the application, the Health Director determines the proposed design does not meet the requirements of this chapter, or soil or geological conditions are such as to preclude safe and proper operation of the desired installation or installations, a construction or alteration permit shall be denied. (e) A construction or alteration permit shall be valid for one year after the date of issuance. A construction or alteration permit can be extended for a period of six months with the payment of applicable fees.
(Ord. 20134 §3; January 12, 2015: prior Ord. 17939 §4; November 26, 2001: Ord. 12368 §1; August 28, 1978: Ord. 9150 §4; January 16, 1967)