§ 27.56.120 — Certificate; Approval or Denial
Lincoln, Nebraska Municipal Code (enCodePlus online edition as published 2026-11-08 (history notes seen through Ord. 21775, Sept. 15, 2025)) · Lincoln Municipal Code § 27.56.120
Corpus is an independent public-information project, not the official City of Lincoln website. Stable reference: corpuslaw.us/code/acafee45-3f83-4df2-8815-d40fd4a73738
27.56.120 Certificate; Approval or Denial.
Within forty-five days of the hearing, the Nebraska Capitol Environs Commission shall approve or deny the application. The Commission may: (a) Issue a certificate of “appropriateness” after adopting a finding that the proposed work meets the Standards and would not unduly hinder the protection, enhancement, perpetuation, and use of the Capitol Environs District; (b) Issue a certificate of “exception on grounds of hardship” after adopting a finding that refusal to issue the certificate would create an extreme hardship on the applicant, and that the plight of the applicant is due to unique circumstances, and that the potential hardship is the result of the application of the ordinance and is not the result of any act or omission by the applicant; (c) Refuse to issue a certificate, after adopting a finding that the application is not consistent with the purpose of this ordinance and of the Standards, and does not meet any of the above criteria. The Nebraska Capitol Environs Commission's decision must be accompanied by written findings of fact. No change shall be made in the application for any building permit or in plans for other regulated work after issuance of a certificate by the Commission or the Commission Chair without resubmittal of the application and approval in the same manner as provided above.
(Ord. 20446 §15; February 13, 2017: prior Ord. 16698 §3; November 14, 1994)
Ask a question about Lincoln law
Corpus searches the Lincoln sections it holds and shows the ones that match, with their citations. Free, no sign-in.