§ 28.01.080 — SWPPP Inspections

Lincoln, Nebraska Municipal Code (enCodePlus online edition as published 2026-11-08 (history notes seen through Ord. 21775, Sept. 15, 2025)) · Lincoln Municipal Code § 28.01.080

Corpus is an independent public-information project, not the official City of Lincoln website. Stable reference: corpuslaw.us/code/31cac4f1-b5e8-44a8-b7e2-1f2fb68b378a

28.01.080 SWPPP Inspections.

It shall be the duty of the permittee to ensure that routine inspections are conducted and that the BMPs on the site are maintained. The permittee shall secure a right of entry to each site within the boundaries of the permit and conduct routine inspections in conformance with the current NDEE NPDES General Permit requirement for SWPP inspection intervals. Inspections shall be conducted by qualified individuals who are knowledgeable in the principles and practices of erosion and sediment control. A qualified individual shall possess the skills to assess conditions at the site that could impact stormwater quality and to assess the effectiveness of any BMPs selected to control stormwater discharges. A log of these inspections shall be retained with the SWPPP, along with photographs or other supporting information. Any deficiencies or discrepancies with actual site conditions shall be noted in a report of the inspection and include any action taken to correct the deficiency or discrepancy. Inspection reports and follow-up documentation regarding violations and associated corrective actions shall be submitted to the City upon request. The inspection report shall include the following minimum information: (a) Inspectors name and title; (b) The project's permit number; (c) The project's name as listed on the NOI application; (d) Date and time of inspection; (e) Weather information for the period since the last inspection (or since commencement of construction activity if this is the first inspection) including a best estimate using publicly accessible data of the approximate amount of rainfall for each storm event (in inches); (f) Description of discharges (if any); (g) Location of discharges and other pollutants from the site; (h) Observations relative to the effectiveness of the BMPs; (i) Location of BMPs that need to be maintained and/or failed; (j) Monitoring results (if requested); (k) Records of grading activities since last inspection; (l) Locations of where additional BMPs are needed that did not exist at the time of inspection; (m) Corrective action that require changes to the SWPPP and the date the plan changes were implemented; (n) Actions necessary and taken to correct deficiencies; and (o) Signature of the person performing the inspection or an authorized representative with the following certification statement: “I certify, under penalty of law, that this inspection report and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment for knowing violations.” A record of each inspection and of any actions taken must be retained as part of the SWPPP for at least three (3) years from the date that permit coverage expires or is terminated. Any delay in the replacement or maintenance of non-functional BMPs beyond the next storm event shall be documented in the SWPPP with sufficient detail explaining the reason for delay, and alternate BMPs must be implemented as soon as possible. Where areas have been identified in the SWPPP to either have frozen ground conditions and construction has been suspended or have undergone stabilization while work on other portions of the site is ongoing, the permittee may reduce inspections of these areas to once per calendar month as long as the described conditions exist. Reduced inspection frequency does not relieve the permittee of the maintenance responsibilities during interim periods. (: Ord. 19671 §7 February 6, 2012: Ord. 18949 §8; June 25, 2007).

(Ord. 21394 §6; January 09, 2023)

Ask a question about Lincoln law

Corpus searches the Lincoln sections it holds and shows the ones that match, with their citations. Free, no sign-in.