§ 735-19: Statement of work done.
A. Within 30 days after completion of the work, each contractor for the required work shall prepare a written statement and account, in duplicate, signed by the contractor, setting forth the following: (1) The name of each contractor. (2) A full and particular survey and measurement of the work done. (3) The date and quantity of work done and the total costs thereof. (4) The proportion of the cost and expense for which each and every owner of the real estate fronting on the street or any part thereof is liable under the contract or contracts aforesaid. (5) The name or names of each owner or reputed owner of the real estate in front of which said work was done and, as nearly as may be, an accurate description and location of each of said pieces of real estate. B. One signed copy of the aforesaid statement and account shall be filed with the Department of Planning and Development and the other with the Department of Finance. Such statement and account shall be regularly entered in the books to be provided for and kept for such purposes. C. After the aforesaid statement and account shall have been regularly recorded as set forth in Subsection B and is found by the City Engineer to be correct, it shall be signed by him and the contractor or contractors and attested by the Director of Department of Planning and Development.
Ask a question about Camden law
Corpus searches the Camden sections it holds and shows the ones that match, with their citations. Free, no sign-in.