§ 870-285: Final major site plan details.

A. Prior to issuance of a certificate of completeness or scheduling of a final plat of a major site plan for public hearing, the Planning Board or Zoning Board of Adjustment shall determine that the following have been submitted in proper form. The Division of Planning and Zoning may schedule a final site plan for consideration by the municipal agency upon submission of the following: (1) The City Engineer's or Board Consultant's report. (2) The application for state wetlands approval, if required. (3) The application for a stream encroachment permit, where required. (4) Where applicable, a copy of the permit issued or, if the permit has not been issued, the application filed with the New Jersey Department of Environmental Protection and copies of the environmental impact statement and any attachments thereto filed in accordance with the provisions of the Act or, in the alternate, a statement issued by the Department of Environmental Protection that the proposed development is exempt from the Act. (5) Where applicable, documents ensuring compliance with any and all requirements as provided for by the New Jersey Environmental Justice Law, N.J.S.A. 13:1D-157 et seq., and the New Jersey Department of Environmental Protection regulations, N.J.A.C. 7:1C et seq., Environmental Justice, and shall include, but not be limited to, an environmental justice impact statement which refers to a systematic, interdisciplinary and integrated assessment of environmental and public health conditions in an overburdened community that identifies and analyzes 1) existing environmental and public health stressors; 2) any adverse environmental and public health stressors; 3) the presence or absence of adverse cumulative stressors; 4) potential environmental and public health stressors associated with a facility; 5) whether the facility can avoid causing a disproportionate impact; 6) the measures the facility will propose to implement to avoid or address any disproportionate impact; and 7) where applicable, how the new facility serves a compelling public interest in the overburdened community. This environmental justice impact statement shall take into account both the residents in the area of the development as well as all other residents in the City of Camden to ensure that each resident has a safe and healthy environment in which to live. (6) Other submittals that may be required by the Planning Board, Zoning Board of Adjustment or federal, state, county or municipal law. (7) Required application fees as set forth in this chapter. (8) Fifteen copies of a plat and attachments meeting the requirements set forth below. B. The final plat shall include all data required for the preliminary plat of the major site plan and shall be drawn to incorporate all changes required as a condition of preliminary approval and shall be drawn by persons and to specifications as required for a preliminary plat and shall be titled "Final Plat — Major Site Plan." Any approval of an application for development of a final plat of a major site plan shall be subject to the following conditions being satisfied, within a period of time specified by the Planning Board or Zoning Board of Adjustment, prior to the signing of the plat or issuance of a development permit: (1) Payment of any outstanding real estate taxes and property improvement assessments. (2) Submission of additional prints of the plat map and attachments for distribution, if required. (3) Publication of a notice of the decision of the Board by the administrative officer (Planning Board or Zoning Board of Adjustment Secretary) within the time set forth in this chapter. (4) Final Camden County Planning Board approval, if not previously granted. (5) Any other utility company final approval. (6) Final electric, gas, telephone and cable service agreements. (7) Certification of soil erosion and sediment control plans, if not previously obtained. (8) Fire Department approval, if not previously obtained. (9) Granting of a New Jersey Department of Environmental Protection permit as required. (10) Granting of any required construction permits. (11) Posting of required performance guaranties. (12) Payment of required inspection fees. (13) Certification from the City Tax Collector that all taxes are paid up to date. (14) Certification that the applicant is the owner of the land or his properly authorized agent, or that the owner has given his consent under an option agreement. (15) Approval signatures. (a) Chairman. (b) Secretary. (c) City Engineer. (d) Zoning Officer/Administrative Officer. (16) Such other information as the municipal agency may require or request during the review of the application for classification and approval as a major subdivision plan.

[Added 11-16-2023 by Ord. No. MC-5475 ]