For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 16.08.080 — Time

Municipal Code of the City of New Brunswick, New Jersey (Codified through Ordinance No. O-042606, passed April 15, 2026. (Supp. No. 39, Update 2)) · New Brunswick City Code § 16.08.080

Corpus is an independent public-information project, not the official City of New Brunswick website. Stable reference: corpuslaw.us/code/5e932358-b69b-4fcc-aa6a-8a1c0a328561

16.08.080 - Time.

A. Minor Subdivisions. Minor subdivision approvals are granted or denied within forty-five (45) days of the date of submission of a complete application to the planning board or within such further time as may be consented to by the applicant. Approval of a minor subdivision expires one hundred ninety (190) days from the date of planning board approval, unless, within such period, a plat in conformity with such approval and the provisions of the "Map Filing Law," or a deed clearly describing the approved minor subdivision, is filed by the developer with the county recording officer, the city engineer and the city tax assessor. Any such plat or deed must be signed by the chairperson and secretary of the planning board before it will be accepted for filing by the county recording officer. B. Preliminary Approval Major Subdivision. Upon submission of a complete application for a subdivision of ten (10) or fewer lots, the planning board grants or denies preliminary approval within forty-five (45) days of the date of such submission or within such further time as may be consented to by the developer. Upon submission of a complete application for a subdivision of more than ten (10) lots, the planning board grants or denies preliminary approval within ninety-five (95) days of the date of such submission or within such further time as may be consented to by the developer. Otherwise, the planning board is deemed to have granted preliminary approval for the subdivision. C. Ancillary Powers. Whenever the planning board is called upon to exercise its ancillary powers before the granting of a variance as set forth in Section 16.08.070(H), the planning board shall grant or deny approval of the application with one hundred twenty (120) days after submission by the developer of a complete application or within such further time as may be consented to by the applicant. Failure of the planning board to act within the period prescribed constitutes approval of the application, and a certificate of the administrative officer as to the failure of the planning board to act is issued on request of the applicant. D. Final Approval. Application for final subdivision approval is granted or denied within forty-five (45) days of submission of a complete application or within such further time as may be consented to by the applicant. E. Final approval of a major subdivision expires ninety-five (95) days from the date of signing of the plat, unless within such period, the plat has been duly filed by the developer with the county recording officer. The planning board may, for good cause shown, extend the period for recording for an additional period not to exceed one hundred ninety (190) days from the date of signing of the plat.

(Ord. O-060805 § 1, 2008; prior code § 25-1.8)

Ask a question about New Brunswick law

Corpus searches the New Brunswick sections it holds and shows the ones that match, with their citations. Free, no sign-in.