§ 435-48: Time for commencement of work; automatic termination of permit; renewal of terminated permit.
A. Work for which a permit has been issued pursuant to this article shall commence within 30 days after the issuance of the permit therefor. B. If not so commenced, the permit shall be automatically terminated and the permit fee, inspection fee and any cash deposit shall be refunded to the permittee, with the exception of the ten-dollar application fee. C. Permits thus terminated may be renewed upon the payment of an additional application fee and the required permit and inspection fees as determined by the Engineer and defined within this article.
Ask a question about Paterson law
Corpus searches the Paterson sections it holds and shows the ones that match, with their citations. Free, no sign-in.