§ 24-185 — Change orders
Municipal Code of the City of Las Cruces, New Mexico (Supp. No. 34: codified through Ordinance No. 3114, adopted June 1, 2026) · Las Cruces Municipal Code § 24-185
Corpus is an independent public-information project, not the official City of Las Cruces website. Stable reference: corpuslaw.us/code/837fbb19-3db2-4fe3-91ab-b72beb28084b
Sec. 24-185 - Change orders.
(a) Changes in time. Extensions of time on construction contracts or professional/technical service contracts, may be granted by the project manager, subject to appropriate approvals, on a case-by-case basis for the following reasons: (1) One additional day for each delay in which the contractor could not perform contractual work and subsequent days as may be required to repair work damage by weather, as defined in General Conditions for Construction Contracts, 2004, during the term of the contract; (2) City-requested changes to project specifications that incur time as a result; (3) Other circumstances in which the city believes such an extension of time is in the best interest of the project and must be approved by the department director; (4) Limitations on extensions of time addressed by this policy are as follows: a. An increase of 30 contractual days to the original contract time, shall be approved by the program manager; b. An increase of 31 to 60 contractual days to the original contract time shall be approved by the appropriate department director; c. An increase of more than 60 contractual days to the original contract time, shall be approved by the city manager. (b) Changes in cost. (1) Any changes in contract cost which includes base contract amount, contingency, and NMGRT, require the following approvals: Change | Approver Less than 5% | Program manager More than 5% less than 10% | Department director More than 10% less than 15% | Assistant city manager More than 15% | City manager Contract approved by city council | City council Exceeds approved budget amount | City council (2) Budgetary authority. In no case does city staff or management have the ability to increase the budget at the fund level, including usage of unbudgeted fund balance, without city council approval. (3) Proposed construction work that deviates from the contract drawings and/or specifications shall be initiated with a field notice followed by a duly authorized change order when there is a change in cost and approved by the appropriate approver and based on current thresholds.
(Ord. No. 2973, § I(Exh. A), 6-7-21; Ord. No. 3026, § I(Exh. A), 2-21-23)
Ask a question about Las Cruces law
Corpus searches the Las Cruces sections it holds and shows the ones that match, with their citations. Free, no sign-in.
