§ 32-38 — Street lights—Specifications for installation
Municipal Code of the City of Las Cruces, New Mexico (Supp. No. 34: codified through Ordinance No. 3114, adopted June 1, 2026) · Las Cruces Development Code § 32-38
Corpus is an independent public-information project, not the official City of Las Cruces website. Stable reference: corpuslaw.us/code/383cb38a-db48-4fc3-8667-4b6383a6d117
Sec. 32-38. - Street lights—Specifications for installation.
(a) Conduit. Conduit shall be one and one-half inch (38.10mm) PVC Type, Schedule 40. Installation depth shall be 18 inches (457.20mm) minimum and 24 inches (609.60mm) maximum. Variation from these depths, when crossing other utilities to maintain twelve inches (604.80mm) separation, is allowable when approved by the public works director or his/her designee. Location and alignment shall be as shown on standard construction drawing, unless otherwise specified on the subdivision construction plans. (b) Backfill. Backfill shall be as stated in the city standard specifications for road construction, as amended. (c) Foundations for street lights. STREET LIGHT FOUNDATION REQUIREMENTS Street Light Pole Height | Foundation Size Specifications 25′ (7.62m) pole with 6′ (1.83m) arm | 2′ × 2′ × 3′ (0.61m × 0.61m × 0.91m) 35′(10.66m) pole with 8′ (2.43m) arm | 3′ × 3′ × 4′ (0.91m × 0.91m ×1.22m) Dual arm pole | 3′ × 3′ × 5′ (0.91m × 0.91m × 1.52m) All poles shall require bolts with nuts and washers (furnished by the city with bolt template); a ground rod five-eighths of an inch × eight feet (15.88mm × 2.44m); one-half inch (12.70mm) rebar reinforcement, approximately forty linear feet (12.19m), as shown on construction plans; one and one-half inch (38.10mm) PVC conduit for continuous circuit; and, Class A 3,000 PSI (20,684.27kPa) concrete. Material test of concrete shall be made, when specified by the public works director or his/her designee. d. Joint use of underground trench. Joint use of trench for the installation of electrical service by El Paso electric company, and/or for street light circuits, is acceptable when approved by both the city and El Paso electric company. e. Completion of street light system. When development of housing begins, and subject to notification given to the city public works department by the contractor/developer, the city shall complete the installation of the street light system to full operation.
(Ord. No. 949, § 2.3, 9-8-87; Ord. No. 1224, § 1, 3-18-91; Ord. No. 1745, § I, 6-7-99; Ord. No. 1929, §§ I, II, 8-5-02)