§ 28-104.2.6 Deferred submittal.
With the prior approval of the department, the applicant may defer submittal of portions of the design until a specified period of time after the issuance of a permit. The applicant shall list the deferred submittal items on the initial application for construction document approval. The deferred submittal items shall not be constructed or installed until the design and submittal documents for the item have been approved by the department. The owner and permit holder shall proceed at their own risk with the construction operation and without assurance that a permit for the entire structure will be granted and the approval of all construction documents shall be conditioned upon and subject to compliance with the requirements of this code and other applicable laws and rules in effect at the time of issuance of the associated permit or place of assembly certificate of operation. (Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022) Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
Ask a question about New York law
Corpus searches the New York sections it holds and shows the ones that match, with their citations. Free, no sign-in.