§ 212-a — Period of maintenance; acceptance of work
Municipal Code of the City of White Plains, New York (Codified through Ordinance of October 5, 2026. (Supp. No. 79, Update 2)) · White Plains City Charter, art. VII, § 212-a
Corpus is an independent public-information project, not the official City of White Plains website. Stable reference: corpuslaw.us/code/f1e9440b-584e-4837-b0ec-9729a30fcb2d
Sec. 212-a. - Period of maintenance; acceptance of work.
Any contractor furnishing public work to the city of White Plains shall be responsible for the entire work until the time of its acceptance as hereinafter provided and shall also keep and maintain every portion of it in perfect order and repair for a period of six (6) months after the completion of said work or, in the discretion of the commissioner of public works, after substantial completion of said work, excepting in regard to such damages as may be directly caused by the city of White Plains, its agents or servants, and excepting in cases where in the opinion of the commissioner of public works, by the nature of the work, no maintenance is involved. If the termination of said six (6) month period shall fall within the months of December, January, February, March or April, the period of maintenance shall extend to the first day of May next thereafter. At the conclusion of the said period of maintenance or, if there be no period of maintenance as provided hereinabove, then upon the completion of the work as provided hereinabove the work may be accepted provided it be then in good order and repair, that it conform entirely with the required lines, grades, and dimensions, and if all other obligations on the part of the contractor under his contract have been fulfilled. If at any time during the period of maintenance the contractor, after notice by the engineer, shall fail to promptly repair and/or make good any defect or damage in the work, then and in that case the commissioner of public works shall have the right to cause such defect or damage to be repaired and made good by the city's own forces or by such other parties as may be selected by said commissioner, and to charge to the contractor the cost of all labor, materials, plant, equipment and other incidental expenses necessary to such repair and making good. Said cost shall be deducted from the contractor's retained percentage. All questions or disputes in regard to repairs required during the period of maintenance shall be resolved by the commissioner of public works, whose determination shall be conclusive.
(L.L. No. 4-1967, § 78)
Ask a question about White Plains law
Corpus searches the White Plains sections it holds and shows the ones that match, with their citations. Free, no sign-in.