§ 47-6 — Costs of sewers in private developments

Oklahoma City Municipal Code (Supp. No. 5, Update 1: codified through Ordinance No. 28070, adopted April 21, 2026) · Oklahoma City Municipal Code § 47-6

Corpus is an independent public-information project, not the official City of Oklahoma City website. Stable reference: corpuslaw.us/code/fe9e7194-e544-40ff-8223-96de4384b1fb

§ 47-6. - Costs of sewers in private developments.

(a) Any sanitary sewer mains or submains serving or within any new subdivision shall be constructed to sufficient size and capacity to accommodate the anticipated conditions resulting from gravity flow from or to any mains or submains intended to serve that subdivision and any other property that may be connected into said mains or submains at a future date. (b) The property owner shall pay a proportionate share of the construction based on the cost of the project minus lift stations and plant cost divided by diameter of pipe used, all multiplied by 8. The construction of such sanitary sewer mains or submains in excess of the cost required to construct eight-inch-diameter mains or submains shall be borne by the City. (c) Participation by the City in any costs shall be subject to availability of voter-approved bond funds. (d) If the developer desires to award his own contract for any of the sanitary sewer facilities, then the entire cost shall be paid by the developer with no participation by the City. (e) Payment to the City for engineering services shall be in accordance with Chapter 60, the General Schedule of Fees.

(Code 1970, § 31-5; Code 1980, § 47-4)

Ask a question about Oklahoma City law

Corpus searches the Oklahoma City sections it holds and shows the ones that match, with their citations. Free, no sign-in.