§ 2.18.50 — Permit Recording
Municipal Code of the City of Corvallis, Oregon (Codified through Ordinance No. 2026-31, enacted October 19, 2026. (Supp. No. 70, Update 2)) · Corvallis Land Development Code § 2.18.50
Corpus is an independent public-information project, not the official City of Corvallis website. Stable reference: corpuslaw.us/code/c9dd8c1d-a2d4-4a88-8f2d-25efc63254bc
Section 2.18.50 - Permit Recording.
Within 30 days after a Solar Access Permit and Building Permit for the solar energy system have been granted, the Director shall file the Solar Access Permit with the Benton County Recorder in such form as required by state law. The permit shall include approved solar envelopes for affected properties, exemptions to or limits on the solar right being created, and the solar collector drawing, sunchart, and site plan.