§ 9.04.050 — Duration of Permit
Municipal Code of the City of Hillsboro, Oregon (Codified through Ordinance No. 6513, adopted March 3, 2026 (Supp. No. 2)) · Hillsboro Municipal Code § 9.04.050
Corpus is an independent public-information project, not the official City of Hillsboro website. Stable reference: corpuslaw.us/code/63a62392-5dce-46ca-b56b-de27266c538d
9.04.050. - Duration of Permit.
A. All street improvement work must be completed within 18 months of the date the street improvement permit is issued. B. Failure to comply with HMC 9.04.050(A) is cause for the Manager to take appropriate measures to complete the work.
(Ord. 6059, § 1, 2013; Ord. 6258, § 1, 2018)