§ 21.20.010 — Location of Main

Portland City Code (non-zoning titles; Title 33 separately); partial · Portland City Code § 21.20.010

Corpus is an independent public-information project, not the official City of Portland website. Stable reference: corpuslaw.us/code/39e40acd-ec55-41a3-900c-b9180486f576

21.20.010 Location of Main.

A. Where a water main may be installed. A water main may be installed in public right-of-way or easements.

B. Water main in easements. The City Administrator may authorize water main installation in an easement if the following conditions are met:

1. The easement is at least 20 feet wide (for a main that is 12 inches or less in diameter) and the outer edge of the main is a minimum of six feet from the nearest edge of the easement. Easements for a larger main must be reviewed individually and must be at least 30 feet wide, and the outer edge of the main must be a minimum of 12 feet from the nearest edge of the easement and any structure;

2. The edge of the easement is at least two feet from the property-side meter stop;

3. Any trees proposed to be planted in the water easement must provide a minimum separation at maturity of 10 feet and may only be planted along the outer edge of the easement;

4. There is no parking or structures allowed on or over the easement where the water main is to be placed;

5. The new water main is at least 50 feet long;

6. The easement extends a minimum of eight feet beyond fire hydrants, five feet beyond the end of the main and two feet beyond services that are one inch in diameter or smaller; and

7. The Water Bureau may have 24-hour unobstructed access to all parts of the easement main and appurtenances installed to support the main system.

The City Administrator may authorize additional conditions or exceptions to these conditions.

C. A water main must extend at least five feet past either the closest property line or the location of the proposed service, whichever is farther.

D. The City Administrator may determine that the existing main is not close enough, large enough or in the wrong location to serve a property or development. If that happens, the applicant requesting new service may apply for the main to be built or improved.

The applicant must pre-pay the Water Bureau to build the new main or make the existing main larger. The Water Bureau determines how much this costs, based on the site and the annual rates ordinance. To estimate the cost, the Water Bureau will determine the most direct route through a public right-of-way or approved easement.

E. The Water Bureau will determine main size, type and route based on long-term system needs.

The applicant must pay for the size and route specified by the Water Bureau. The applicant must pay for a main large enough to meet their demand, or a main that is at least six inches in diameter.

If the Water Bureau chooses to install a larger main than the project requires, chooses an alternate route for the main, or chooses to install other improvements at the same time, the Water Bureau will pay the extra costs.

F. The City Administrator will establish, maintain and enforce engineering and technical standards to plan, design, construct, operate, maintain and protect all of the City’s public drinking water system, related infrastructures and assets.