24.25.020 Permit Information Required.
The applicant must file with Portland Permitting & Development an application for a permit to move the structure, it must be signed by the owner or the owner’s authorized agent, and must contain a description of the building to be moved, the location where it is to be moved, and the use and occupancy proposed, in addition to the information required by Section 24.10.070 of this Title regarding foundation or other work at the final location.