For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 24.25.020 — Permit Information Required

Portland City Code (non-zoning titles; Title 33 separately); partial · Portland City Code § 24.25.020

Corpus is an independent public-information project, not the official City of Portland website. Stable reference: corpuslaw.us/code/7c898771-35eb-4b0a-8679-1e69ff3280dc

24.25.020 Permit Information Required.

The applicant must file with Portland Permitting & Development an application for a permit to move the structure, it must be signed by the owner or the owner’s authorized agent, and must contain a description of the building to be moved, the location where it is to be moved, and the use and occupancy proposed, in addition to the information required by Section 24.10.070 of this Title regarding foundation or other work at the final location.

Ask a question about Portland law

Corpus searches the Portland sections it holds and shows the ones that match, with their citations. Free, no sign-in.