§ 18-3-39 — Affirmative defenses to discharge violations

Code of Ordinances, City of Amarillo, Texas (Supp. No. 81: codified through Ordinance No. 8226, enacted December 9, 2025) · Amarillo City Code § 18-3-39

Corpus is an independent public-information project, not the official City of Amarillo website. Stable reference: corpuslaw.us/code/e1add569-db7b-4f85-923e-f0091263acc7

Sec. 18-3-39. - Affirmative defenses to discharge violations.

(a) A user shall have an affirmative defense to any type of enforcement action brought against it for noncompliance with this chapter if it can prove that it did not know, or have reason to know, that its discharge, alone or in conjunction with discharges from other sources, would cause pass through or interference, and that either: (1) A local limit exists for each pollutant discharged and the user was in compliance with each limit directly prior to, and during, the pass through or interference; or (2) No local limit exists, but the discharge did not change substantially in nature or constituents from the User's prior discharge when the POTW was in regularly in compliance with its TPDES permit, and in the case of interference, was in compliance with applicable sludge use or disposal requirements. (b) Act of God. If a person can establish that an event that would otherwise be a violation of a statute within the City's jurisdiction or a rule adopted or an order or a permit issued under such a statute was caused solely by an act of God, war, strike, riot, or other catastrophe, the event is not a violation of that statute, rule, order, or permit. (c) Bypass. (1) For the purposes of this section: a. "Bypass" means the intentional diversion of wastestreams from any portion of a user's treatment facility. b. "Severe property damage" means substantial physical damage to property, damage to the treatment facilities which causes them to become inoperable, or substantial and permanent loss of natural resources which can reasonably be expected to occur in the absence of a bypass. Severe property damage does not mean economic loss caused by delays. (2) A User may allow any bypass to occur which does not cause pretreatment standards or requirements to be violated, but only if it also is for essential maintenance to assure efficient operation. These bypasses are not subject to the provisions of Subsections (3) and (4) of this section. (3) Bypass Notifications. a. If a User knows in advance of the need for a bypass, it shall submit prior notice to the director, at least ten (10) days before the date of the bypass, if possible. b. A User shall submit oral notice to the Director of an unanticipated bypass that exceeds applicable pretreatment standards within twenty-four (24) hours from the time it becomes aware of the bypass. A written submission shall also be provided within five (5) days from the time the User becomes aware of the bypass. The written submission shall contain a description of the bypass and its cause; the duration of the bypass, including exact dates and times, and, if the bypass has not been corrected, the anticipated time it is expected to continue; and steps taken or planned to reduce, eliminate, and prevent reoccurrence of the bypass. The Director may waive the written report on a case-by-case basis if the oral report has been received within twenty-four (24) hours. (4) Provided, however: a. Bypass is prohibited, and the Director may take an enforcement action against a User for a bypass, unless: i. Bypass was unavoidable to prevent loss of life. personal injury, or severe property damage; ii. There were no feasible alternatives to the bypass, such as the use of auxiliary treatment facilities, retention of untreated wastes, or maintenance during normal periods of equipment downtime. This condition is not satisfied if adequate back-up equipment should have been installed in the exercise of reasonable engineering judgment to prevent a bypass which occurred during normal periods of equipment downtime or preventive maintenance; and iii. The User submitted notices as required under paragraph (3) of this section. b. The Director may approve an anticipated bypass, after considering its adverse effects, if the Director determines that it will meet the three (3) conditions listed in paragraph (4) of this section.

(Ord. No. 7222, § 2, 7-13-2010)

Ask a question about Amarillo law

Corpus searches the Amarillo sections it holds and shows the ones that match, with their citations. Free, no sign-in.