§ 5.04 — Right-of-Way Permit Requirements

Code of the City of Arlington, Texas (City Secretary chapter PDFs as posted 2026-11-07, each current through the ordinance named on its cover, with the City Secretary's adopted-not-yet-codified Ordinances 25-063, 25-069, 25-073, 25-074, 25-075, 25-084, 26-003, 26-004, 26-019, 26-024 and 26-027 applied; Anti-Discrimination chapter not included) · Arlington City Code, Right-of-Way Management Chapter, § 5.04

Corpus is an independent public-information project, not the official City of Arlington website. Stable reference: corpuslaw.us/code/3e44fdfa-c8c1-4be6-9271-e7b874b0b794

Section 5.04 Right-of-Way Permit Requirements

The following procedures and requirements govern the application for and issuance of a permit to perform construction within the public right-of-way: A. Permit Application 1. A permit application must be made in writing on a form obtained from the City. The application must be signed and submitted by the permittee on behalf of the owner of the facility for which the permit is requested. The application for permit must be filled out completely and accurately. Any omissions or inaccuracies on the form may be cause for denial of the permit at the City’s discretion. 2. A permit application must be submitted to the City in accordance with the timeframes specified in the Public Right-of-Way Permitting and Construction Manual. 3. The City shall state on the permit any reasonable additional restrictions or requirements determined necessary. These additional restrictions or requirements shall be considered a part of the permitted activity. 4. The permittee shall, as an express condition of the permit, comply in all respects with the requirements prescribed for the permitted activity in the Public Right-of-Way Permitting and Construction Manual and with all other City ordinances and state or federal laws or regulations affecting the permitted activity. 5. Reimbursement of Costs a. Except as provided by Subsection (A)(5)(b), the permittee shall, as an express condition of the permit, reimburse the City for the actual direct and indirect costs associated with the permit. Reimbursement to the City shall be made within thirty (30) calendar days of the receipt of an invoice from the City. b. Subsection (A)(5)(a) does not apply to a permittee when state law, this Code of Ordinances, a franchise ordinance, or agreement with the City provides that a fee may not be charged for construction within the public right-of-way, establishes the amount of the fee that may be charged, or provides that the City’s actual direct and indirect costs may not otherwise be reimbursed, including a permittee that is a certificated telecommunications provider operating under Texas Local Government Code Chapter 283, a network provider operating under Texas Local Government Code Chapter 284, a cable or video service provider operating under Texas Utilities Code Chapter 66, or a gas utility company or electric utility company operating pursuant to a franchise ordinance under the Utilities Chapter of this Code of Ordinances. B. Construction Plan Drawings The permit application on any project must include submittal of construction plan drawings. The plans must conform to the standards set forth in the Public Right-of-Way Permitting and Construction Manual. When required by the Texas Engineering Practice Act, as amended, the plans must be sealed by a professional engineer licensed to practice in the State of Texas. C. Utility Structures 1. Above ground utility structures shall meet the following requirements: a. Above ground utility structures exceeding two feet in height shall not be placed within any intersection visibility triangle, as defined in the City’s Unified Development Code or Design Criteria Manual. b. Above ground utility structures, not including poles, less than 60 cubic feet in volume, with no dimension greater than six feet, may be placed within the public right-of-way without screening. c. Above ground utility structures, not including poles, equal to or greater than 60 cubic feet in volume, and less than 240 cubic feet in volume, and less than seven feet in height shall: i. Be placed within a public or private utility easement outside the street right-of-way; and ii. Be screened on all sides except for the sides containing openings for access to the structure. d. Structures equal to or greater than 240 cubic feet in volume, or more than seven feet in height shall be located in a private utility easement or other private property and shall be screened on all sides except for the sides containing the openings for access to the structure, and shall be subject to requirements of the Unified Development Code. e. The dimensions of the supporting foundation or pad shall allow for existing and proposed sidewalks. f. Above ground utility structures shall comply with all requirements of other City ordinances and other state and federal laws and regulations. Public Service Provider shall be responsible for obtaining other permits, as required. g. Screening as required in this Section shall consist of a barrier of stone, brick, pierced brick or block, uniformly colored wood or other permanent material of equal character, density and design, at least 6’ in height, or combination of two or more materials. Screening shall not exceed six feet in height. No separate permit will be required for any approved screening wall. Screening shall be placed so that it does not interfere with visibility triangles or create other traffic-related visibility obstructions. h. The exterior surfaces of all utility structures and screening shall be maintained free of graffiti and other defacements such as posters, stickers, decals, and signs, except those placed on the structure by the utility company for identification. The exterior finish shall be maintained free of visible deterioration. i. The utility structure shall be clearly marked with the owner’s name and contact information. 2. Below ground utility structures may be allowed in the right-of-way if space is available. 3. In reviewing the utility structures the City will consider the following: a. Size, location, and impact of the proposed structure; b. The structure’s coordination with existing and proposed public facilities; and c. Availability of remaining right-of-way. 4. Request for Waiver - A request for a waiver of the requirements of this Section 5.04(C) may be made to the City. a. The request for a waiver must include a detailed justification for the waiver, including the lack of existing sites not within the public right-of-way; alternative sites sought and reviewed; and proof that compliance with the requirement is impractical. b. Within 30 calendar days of receipt of a written request for a waiver, the City may, with sole discretion, grant a waiver for good cause. c. In making this decision, the City shall consider: i. the availability of alternate locations; ii. the size, location, and impact of the proposed facility in the right-of-way at the proposed site; iii. the need to provide services to a property or area to be served by the proposed facility; iv. the need for the proposed size of the proposed facility to provide services to a property or area to be served by the proposed facility; and v. the public health, safety, welfare and convenience. d. The City shall indicate in written communication the basis for granting or not granting any waiver pursuant to this subsection. e. The City’s decision regarding the waiver shall be final. 5. If the City determines that the proposed utility structure cannot be placed within the right-of-way without adversely affecting the integrity of an existing or future facility owned by the City, the City shall have the right to deny the location of a new or replacement utility structure within the said right-of-way. D. Utility Structures on City Property Other Than Right-of-Way In cases where utility structures, except those structures serving solely the City property, will be located on City property other than public right-of-way, the following requirements apply: 1. The application shall be made to the City for execution of a use privilege agreement through the City’s Real Estate Services division. 2. Nothing contained herein, however, shall ever be held or construed to confer upon any person the right to place a utility structure upon City property. The City reserves the right, at its sole discretion, to enter into a Use Privilege Agreement to allow the placement of a utility structure on City property. 3. The City shall not be liable for damages or losses of any kind whatsoever by reason of injury to property or person occasioned by the use of any City property. The City shall have no obligations in regard to the maintenance of any improvements within such City property. The City shall be defended at the cost and expense of the person placing improvements on City property from all claims and demands. 4. The public service provider shall pay City a use fee for use of the property based upon the fair market value as determined by the City’s Real Estate Services Division. In addition to a use fee, the City may request the public service provider to provide network connectivity or conduit to the City. 5. The public service provider shall cooperate with other providers in connection with allowing collocation of facilities within the utility structure. E. Storm Water Pollution Prevention Plan The permittee shall submit with the permit application two sets of a Storm Water Pollution Prevention Plan (SWPPP) to the City in cases where stream crossings are open cut, unless the work is being performed under an SWPPP submitted by another entity. When working under the SWPPP of another entity, the plan shall identify the SWPPP under which the utility is performing the work. In all other cases, the permittee is required to implement erosion control measures for construction activities in accordance with the Storm Water Pollution Control Chapter of the City Code, as amended, and other City ordinances and State or Federal laws and regulations. F. Traffic Control Plan Any work that may impact traffic flow or result in lane closures in any street will require an approved site specific traffic control plan and the closures shall comply with the most current edition of the Texas Manual on Uniform Traffic Control Devices, as amended. The permittee shall submit a site specific traffic control plan, when applicable, to the Department of Public Works and Transportation Traffic Engineering Division and obtain approval prior to the lane closure. G. Trench Safety Plan Trench safety systems shall meet U.S. Occupational Safety and Health Administration Standards.

(Amend Ord 21-031, 6/8/21) (Amend Ord 22-051, 10/25/22)

Ask a question about Arlington law

Corpus searches the Arlington sections it holds and shows the ones that match, with their citations. Free, no sign-in.