§ 6.09.146 — Notification requirements

Code of Ordinances, City of Beaumont, Texas (through Ord. 26-062 adopted 2026-10-06 (eCode360 BE6239 publication, data-code-date 2026-10-06, scraped 2026-11-21)) · Beaumont Code of Ordinances § 6.09.146

Corpus is an independent public-information project, not the official City of Beaumont website. Stable reference: corpuslaw.us/code/629ad973-390c-46f9-b2f6-6e83531187ce

§ 6.09.146: Notification requirements.

(a) The permittee shall publish notices in the local newspaper in the manner and order set forth below: (1) 1st notice - to be published at least three (3) days prior to the start of any seismic testing. Running time - one (1) day. (2) 2nd notice - to be published on the day which seismic testing first begins. Running time - one (1) day. (3) Such work may continue no more than three (3) consecutive working days of nonproduction. If seismic testing does not occur during this time, another notice must be published on the day such work will restart. Additional notices must be republished to coincide with intermittent work. Running time - one (1) day each occurrence. (4) Final notice - to be published when any such seismic testing is approximately fifty percent (50%) complete. Running time - one (1) day. Aforementioned notices shall appear in the classified section under legal notices. The notice shall indicate the scope of operations to be performed and will detail the approximate dates and time (starting and ending) and general location of work to be performed. The city building official shall be notified when the notice has been placed with the newspaper and what dates it will be published. (b) The permittee is required to notify the following entities twenty-four (24) hours prior to the start of seismic testing: Fire department - Fire marshal (409-880-3905)Blasting work only:Engineering division (409-880-3725); andAll residents abutting test route. If more than three (3) consecutive working days of nonproduction occur, the permittee must contact the fire department twenty-four (24) hours in advance of any blasting to be done after a period of intermittent work. In addition, the permittee is required to notify any and all other entities, directly or indirectly, involved through other permits or agreements.

( Ordinance 08-027 , sec. 8, adopted 4/29/08 )