§ 19.11.050 — Deferred construction of improvements in the ETJ

El Paso City Code (Supp. No. 95, Update 4: codified through Ordinance No. 019889, enacted June 23, 2026) · El Paso City Code § 19.11.050

Corpus is an independent public-information project, not the official City of El Paso website. Stable reference: corpuslaw.us/code/96af2e5f-e188-4d9f-a9d0-4d41ada4c4f1

19.11.050 - Deferred construction of improvements in the ETJ.

In order to not create disincentives to development within the city limits of El Paso and to avoid future expenses for the taxpayers of the city to bring newly annexed, developed areas up to city standards, the city will require, where possible, the actual infrastructure required by this title to be installed or constructed. Where such improvements cannot be constructed at the time of plat approval, the city may require cash escrow to offset the future expense in accordance with Chapter 19.08. If the city manager or designee determines that an improvement may not be constructed within ten years, it may waive the requirement for cash escrow for such improvements.

(Ord. 16882 § 2 (part), 2008)

Ask a question about El Paso law

Corpus searches the El Paso sections it holds and shows the ones that match, with their citations. Free, no sign-in.