§ 18-400: Impact fee as condition of development approval; permit issuance.

No final plat for new development shall be released for filing with the appropriate county, or in the cases for which no plat is submitted to the city, whether the property is located inside or outside the corporate boundaries of the city, no application for a utility connection shall be approved and/or no building permit and/or certificate of occupancy shall be issued, without assessment of an impact fee pursuant to this article. No building permit shall be issued, or in the cases for which no plat is submitted to the city, whether the property is located inside or outside the corporate boundaries of the city, no building permit and/or certificate of occupancy shall be issued and/or utility connection made, for new development, until the property owner has paid the impact fee imposed by and calculated herein or a contract for payment is approved by the city and executed by the parties.

( Ordinance 05-07-53 , sec. 2, art. 7, adopted 7/5/05 ; Ordinance 12-03-12 , sec. 2, art. 7, adopted 3/6/12 )