§ 31.174 — Stormwater discharge from construction activities

Code of Ordinances of the City of Garland, Texas (Garland Code of Ordinances, Home Rule Charter and Garland Development Code current through Ordinance 7697 adopted August 17, 2026 (eCode360 publication GA6318, scraped 2026-11-17)) · Garland Code of Ordinances § 31.174

Corpus is an independent public-information project, not the official City of Garland website. Stable reference: corpuslaw.us/code/94b6415f-448b-4927-b132-b28df2181c4b

§ 31.174: Stormwater discharge from construction activities.

(A) General requirements. (1) All operators of construction sites shall use the methodology on best management practices from the most current North Central Texas Council of Government Best Management Practices for Construction Activities Manual to control and reduce the discharge, to the MS4 and to waters of the United States, of sediment, silt, earth, soil, and other material associated with the clearing, grading, excavation, and other construction activities to the maximum extent practicable. (2) Qualified personnel (provided by the operator of the construction site) shall inspect disturbed areas of any construction site that have not been finally stabilized, areas used for storage of materials that are exposed to precipitation, structural control measures, and locations where vehicles enter or exit the site, at least once every seven calendar days and within 24 hours of the end of a storm that is 0.5 inches or greater. All erosion and sediment control measures and other identified best management practices shall be observed in order to ensure that they are operating correctly and are effective in preventing significant impacts to receiving waters and the MS4. Based on the results of the inspection, best management practices shall be revised as appropriate, and as soon as is practicable. (3) The City may require any plans and specifications that are prepared for the construction of site improvements to illustrate and describe the best management practices required by subsection (A) above that will be implemented at the construction site. The City may deny approval of any building permit, grading permit, subdivision plat, site development plan, or any other City approval necessary to commence or continue construction, or to assume occupancy, on the grounds that the management practices described in the plans or observed upon a site inspection by the City are determined not to control and reduce the discharge of sediment, silt, earth, soil, and other materials associated with clearing, grading, excavation, and other construction activities to the maximum extent practicable. (B) One acre disturbances and greater. All operators of sites of construction activity, including clearing, grading, and excavation activities, that result in the disturbance of one or more acres of total land area, or that are part of a common plan of development or sale within which one or more acres of total land area are disturbed, or who are required to obtain a TPDES permit for stormwater discharges associated with construction activity, shall comply with the following requirements: (1) Any operator who intends to obtain coverage for stormwater discharges from a construction site under the TPDES construction general permit shall submit a signed copy of the notice of intent (for 5 acre and larger projects or the site notice for one acre to 5 acre projects) to the City at least two (2) days prior to the commencement of construction activities. If the construction activity is already underway, the notice of intent (NOI) or the site notice shall be submitted within thirty (30) days. For stormwater discharges from construction sites where the operator changes, an NOI shall be submitted at least 2 days prior to when the operator commences work at the site. (2) A stormwater pollution prevention plan (SWPPP) shall be prepared and implemented in accordance with the requirements of the construction general permit or any individual or group TPDES permit issued for stormwater discharges from the construction site, and with any additional requirement imposed by or under this article and any other City ordinance. (3) On a site of one acre or more in total land area (or a site which is impacted by off-site drainage from one acre or more), the SWPPP shall be prepared, signed, and sealed by a registered professional engineer. (4) The SWPPP shall be completed prior to the submittal of the NOI to the City and, for new construction, prior to the commencement of construction activities. The SWPPP shall be updated and modified as appropriate and as required by the construction general permit and this article. Any update or modification to the SWPPP shall be prepared, signed, and sealed by a registered professional engineer, if the original SWPPP was required by subsection (3), above, to have been prepared by a registered professional engineer. (5) A copy of any NOI or construction site notice that is required by subsection (B)(1) shall be submitted to the City in conjunction with any application for a building permit, grading permit, subdivision plat approval, site development plan approval, and any other City approval necessary to commence or continue construction at the site. (6) The City may require any operator who is required by subsection (B)(2) to prepare a SWPPP to submit the SWPPP, and any modifications thereto, to the City for review. Such submittal and review of the SWPPP may be required by the City prior to commencement of or during construction activities at the site. (7) Upon the City’s review of the SWPPP and any site inspection that the director may conduct, the City may deny approval of any building permit, grading permit, subdivision plat, site development plan, or any other City approval necessary to commence or continue construction, or to assume occupancy, on the grounds that the SWPPP does not comply with the requirements of the construction general permit, any individual or group TPDES permit issued for stormwater discharge from the construction site, or any additional requirement imposed by or under this article. Also, if at any time the City determines that the SWPPP is not being fully implemented, the City may similarly deny approval of any building permit, grading permit, subdivision plat, site development plan or any other City approval necessary to commence or continue construction, or to assume occupancy, at the site. (8) Any significant modification to the SWPPP for a site of one acre or more of total land area (or a site which is impacted by off-site drainage from one acre or more) shall be prepared, signed, and sealed by a registered professional engineer as required for the original SWPPP by subsection (B)(3). (9) The SWPPP, with the registered professional engineer’s signature and seal affixed, and with any modifications attached, shall be retained at the construction site from the date of commencement of construction through the date of final stabilization. (10) The operator shall make the SWPPP and any modification thereto available to the City upon request (as well as the EPA and state inspectors). (11) The City may notify the operator at any time that the SWPPP does not meet the requirements of the construction general permit, any applicable individual or group TPDES permit issued for stormwater discharges from the construction site, or any additional requirement imposed by or under this article. Such notification shall identify those provisions of the permit or article which are not being met by the SWPPP, and identify which provisions of the SWPPP require modification in order to meet such requirements. Within seven (7) days of such notification from the City (or as otherwise provided by the City), the operator shall make the required changes to the SWPPP and shall submit to the City a written certification that the requested changes have been made. (12) The operator shall amend the SWPPP whenever there is a change in design, construction, operation, or maintenance, which has a significant effect on the potential for the discharge of pollutants to the MS4 or to the waters of the United States, and which has not otherwise been addressed in the SWPPP, or if the SWPPP proves to be ineffective in eliminating or significantly minimizing pollutants, or in otherwise achieving the general objective of controlling pollutants in stormwater discharges associated with construction activity. (13) Qualified personnel (provided by the operator of the construction site) shall inspect disturbed areas of the construction site that have not been finally stabilized, areas used for storage of materials that are exposed to precipitation, structural control measures, and locations where vehicles enter or exit the site, at least once every seven calendar days and within 24 hours of the end of the storm that is 0.5 inches or greater. Disturbed areas and areas used for storage of materials that are exposed to precipitation shall be inspected for evidence of, or the potential for, pollutants entering the drainage system. Erosion and sediment control measures identified in the SWPPP shall be observed to ensure that they are operating correctly. Where discharge locations or points are accessible, they shall be inspected to ascertain whether erosion control measures are effective in preventing significant impacts to receiving waters or the MS4. Locations where vehicles enter or exit the site shall be inspected for evidence of off-site sediment tracking. (14) Based on the results of the inspections required by subsection (B)(13), the site description and the pollution prevention measures identified in the SWPPP shall be revised as appropriate, but in no case later then seven calendar days following the inspection. Such modification shall provide for timely implementation of any changes to the SWPPP within seven calendar days following the inspection. (15) A report summarizing the scope of any inspection required by subsection (B)(13), and the name(s) and qualifications of personnel making the inspection, the date(s) of the inspection, major observations relating to the implementation of the SWPPP, and actions taken in accordance with subsection (B)(14) above shall be made and retained as part of the SWPPP for at least three years from the date that the site is finally stabilized. Such report shall identify any incidence of noncompliance. Where a report does not identify any incidence of noncompliance, the report shall contain a certification that the facility is in compliance with the SWPPP, the facility’s NPDES permit, and this article. The report shall be certified and signed by the person responsible for making it. (16) The operator shall retain copies of any SWPPP and all reports required by this article or by the TPDES permit for the site, and records of all data used to complete the NOI or construction site notice, for a period of at least three years from the date that the site is finally stabilized. (17) Where a site that disturbs five acres or more (or a common plan of development or sale within which five acres or more are disturbed) has been finally stabilized and all stormwater discharges from construction activities that are authorized by this article and by the TPDES permit for those construction activities are eliminated, or where the operator of all stormwater discharges at a facility changes, the operator of the construction site shall submit to the City a copy of the notice of termination (NOT) that includes the information required for notices of termination by the construction general permit. (18) Upon final stabilization of the construction site, the owner (or the duly authorized representative thereof) shall submit written certification to the City that the site has been finally stabilized. (See definition of final stabilization in this article.) The City may withhold an occupancy or use permit for any premises constructed on the site until such certification of final stabilization has been filed and the City has determined, following any appropriate inspection, that final stabilization has, in fact, occurred and that any required permanent structural controls have been completed.

( Ordinance 5829 , secs. 5, 6 adopted 6/1/04 )