§ 103-202 — Certificate of approval required
Code of Ordinances, City of Harlingen, Texas · Harlingen Code of Ordinances § 103-202
Corpus is an independent public-information project, not the official City of Harlingen website. Stable reference: corpuslaw.us/code/62307a21-9ec7-4be8-9450-cc6657920667
§ 103-202: Certificate of approval required.
It shall be unlawful for any person to make connection from a source of electrical energy to any electrical wiring devices or equipment on an installation for which a permit is required, as set forth in this division, until a certificate of approval has been issued by the chief building official authorizing such connection and the use of such wiring devices or equipment.
( Code 1973, § 8-136 ; Code 1997, § 151.60 ; Ordinance 76-46 , adopted 11/3/1976 ; Ordinance 82-15 , adopted 2/3/1982 )