§ 28.05.022 — Transferring of permit

Code of Ordinances of the City of Lubbock, Texas (Lubbock Code of Ordinances, Charter and Unified Development Code current through Ordinance 2026-O0123 adopted September 22, 2026 (eCode360 publication LU6396, scraped 2026-11-17)) · Lubbock Code of Ordinances § 28.05.022

Corpus is an independent public-information project, not the official City of Lubbock website. Stable reference: corpuslaw.us/code/0e5ec3ff-ee89-4675-8794-0523e22121f9

§ 28.05.022: Transferring of permit.

(a) The building official shall issue only one permit per jobsite for the same or identical work with the following exceptions: (1) Where the current permittee has failed to complete the work, is no longer associated with the project, and such fact is communicated in writing to the building official by the general contractor or owner; (2) Where the building official is notified in writing by the current permittee that his contract for the work is no longer in effect; or (3) Where the building official has been notified in writing by the general contractor or owner that the current permittee originally permitted to do the work at the jobsite has been replaced with a new contractor. (b) In every case where the building official determines that a new permit will be issued to a new contractor, and the scope of the work remains unchanged from that covered by the original permit, the person requiring such permit shall pay a transfer fee of two hundred fifty dollars ($250.00), but in no case more than the fee for the original permit, and no refund shall ever be made on the original permit issued. Where the scope of the work has or will be changed such that a new plan review is necessary, the fee for the reissued permit shall be the same as that for a new project. (c) The building official is authorized to require any other type of evidence from the general contractor, owner or permittee which he deems necessary to determine whether to terminate an existing permit and issue a new permit for the same work. At the discretion of the building official, an investigative inspection of the premises that is the subject of the permit may be required to support a decision to terminate and/or reissue any permit. Fees for said inspection shall be paid in advance as per current fee schedules. (d) The issuance of a new permit under this section shall release the first permitted contractor or builder from any responsibility for compliance with this code for work completed by said contractor or builder and the newly permitted contractor or builder shall become responsible for compliance with this building code for the entire job, including work done by the prior contractor or builder. (e) The building official shall require the owner, general contractor or other interested person to execute an indemnity agreement agreeing to save harmless and defending the city and building official from any and all liability which may be alleged as a result of the issuance of a new permit under this section and to require said agreement to be secured by bonds and insurance deemed appropriate unless a release is signed by all parties. (f) This section shall apply to all types of permits issued by the building official.

( 1983 Code, sec. 6-53 ; Ordinance 2005-O0140 , sec. 1, adopted 12/15/2005 ; Ordinance 2011-O0042 , sec. 3, adopted 5/31/2011 ; Ordinance 2024-O0034 adopted 3/26/2024 )