§ 4-15-75 — Underground and overhead construction
Code of Ordinances, City of Odessa, Texas (Includes legislation through Ord. No. 2026-22 adopted August 11, 2026) · Odessa City Code § 4-15-75
Corpus is an independent public-information project, not the official City of Odessa website. Stable reference: corpuslaw.us/code/47a4e124-0498-44f2-8281-5f40a6dfe792
§ 4-15-75: Underground and overhead construction.
(a) In all sections of the city where all the cables, wires, or other like facilities of public utilities are placed underground, the grantee shall place its cables, wires or other like facilities underground to the maximum extent that the existing technology reasonably permits the grantee to do so and any required licenses can be obtained at reasonable cost. If at any time the city determines that existing wires, cable or other like facilities of public utilities anywhere in the city shall be changed from an overhead to an underground installation, for reasons of public safety or traffic control or to permit a municipal use of the property, the grantee shall also, at the grantee’s sole expense, convert its system to an underground installation. (b) In areas of the city where electrical or telephone systems are installed on poles above ground, the grantee shall have the option of installing the system in like manner above or under ground. (c) A grantee shall promptly locate any buried or underground utilities at the city’s request at no cost to the city. (d) Drop wires in underground service areas that are temporarily placed above ground shall be buried within ten (10) working days of the date and time of the temporary installation, except in those situations where conditions are beyond the control of the grantee.
( Ordinance 99-28 , sec. 1, adopted 6/22/99 ; 1957 Code, sec. 19-164 )
Ask a question about Odessa law
Corpus searches the Odessa sections it holds and shows the ones that match, with their citations. Free, no sign-in.