§ 21-309 — Compliance schedule for meeting categorical pretreatment standards
Code of Ordinances, City of Plano, Texas (Supp. No. 153: codified through Ordinance No. 2025-10-2, adopted October 13, 2025) · Plano City Code § 21-309
Corpus is an independent public-information project, not the official City of Plano website. Stable reference: corpuslaw.us/code/be47eada-3e47-4895-aef5-591504235059
Sec. 21-309. - Compliance schedule for meeting categorical pretreatment standards.
The following conditions shall apply to the schedule required by section 21-308(g). (a) The schedule shall contain increments of progress in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment required for the industrial user to meet the applicable categorical pretreatment standards (e.g., hiring an engineer, completing plans, executing contract for major components, commencing construction, completing construction, etc.). (b) No increment referred to in subsection (a) of this section shall exceed nine (9) months. (c) Not later than fourteen (14) days following each date in the schedule and the final date for compliance, the industrial user shall submit a progress report to the control authority including, at a minimum, whether or not it complied with the increment of progress to be met on such date and, if not, the date on which it expects to comply with this increment of progress, the reason for delay, and the steps being taken by the industrial user to return the construction to the schedule established. In no event shall more than nine (9) months elapse between such progress reports to the control authority.
(Ord. No. 92-7-15, § II(9), 7-13-92)