Sec. 4.08.118 - Time limits
Work under a right-of-way cut permit must be commenced within 14 calendar days of the date of the permit, unless a later date is specified in the permit. Work must be completed within 14 calendar days after initiation of backfilling operations. Additional time will be allowed for completion of the work when approved by the department of public works in accordance with the construction standards on file in the department.
(1996 Code, sec. 4.914; Ordinance adopted 3-20-01)