For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 1-47 — Expiration of a Project or Permit

Code of Ordinances of the City of Sugar Land, Texas (Supp. No. 56: codified through Ordinance No. 2403, adopted June 16, 2026) · Sugar Land Development Code § 1-47

Corpus is an independent public-information project, not the official City of Sugar Land website. Stable reference: corpuslaw.us/code/c741f988-0d22-464b-8fb2-9ce8c5a7273a

Sec. 1-47. - Expiration of a Project or Permit.

A. Project. A Project will expire by operation of law 5 years after an application was filed for the first Permit necessary for the Project if no progress has been made towards completion. B. Permit. A Permit issued by the City expires on the date expressly stated on the face of the Permit. If the Permit does not expressly contain an expiration date, and no progress has been made towards its completion, the Permit will expire by operation of law 2 years after issuance.

Ask a question about Sugar Land law

Corpus searches the Sugar Land sections it holds and shows the ones that match, with their citations. Free, no sign-in.