Sec. 22-77. - Backfill and cleanup.
(a) Within six days after the minimum time set for removal of the forms, or seven days after the placing and finishing of the concrete, the contractor must remove all forms and bracing from the concrete work. He shall also within this time use a portion of the excavated material for backfill around the concrete work and dispose of the excess excavated material. (b) Immediately upon completion of the concrete work, the contractor shall remove all unused materials, dirt and debris. The contractor shall see that the streets, sidewalks and construction site shall be broomed clean and usable by the public.
(Ord. No. 2008-606, § 4, 11-4-08)
Ask a question about Waco law
Corpus searches the Waco sections it holds and shows the ones that match, with their citations. Free, no sign-in.