§ 15-102 — Effect of prior approvals of development plans or issuance of building permits
Code of the City of Chesapeake, Virginia (Supp. No. 148: codified through Ordinance No. 26-O-071, enacted August 11, 2026) · Chesapeake Zoning Ordinance § 15-102
Corpus is an independent public-information project, not the official City of Chesapeake website. Stable reference: corpuslaw.us/code/4e5eb17f-3d99-4d6b-9c1a-7f3395f8fbce
§ l5-l02. - Effect of prior approvals of development plans or issuance of building permits.
A. Authorization of use or structure under building permits issued before change in zoning ordinance; effect when permit lapses. 1. Any building permit which was lawfully issued before the effective date of this ordinance or before any applicable amendment to this ordinance shall be deemed to authorize the construction of a building or structure in accordance with the requirements of the zoning ordinance existing at the time the permit was issued. 2. If such building permit is allowed to lapse or otherwise becomes void, any subsequent construction shall comply with the requirements of the zoning ordinance in effect when the new building permit is issued. B. Authorization of site development under preliminary site plans approved before change in zoning ordinance; lapsing of preliminary site plans. 1. Where the development of a site requires the approval of a site plan by the city, any preliminary site plan which was lawfully approved before the effective date of this ordinance or before any applicable amendment to this ordinance shall be deemed to authorize the location, construction and use of all buildings, structures and related features on the site as they are shown on the preliminary site plan in accordance with the requirements of the zoning ordinance existing at the time the preliminary site plan is approved. 2. Any new zoning ordinance requirements that become effective after the date of preliminary site plan approval but before final site plan approval shall still apply to any such preliminary site plan, provided that such new requirements do not affect the location and dimensions of the buildings and related structures as approved in the site plan. The planning director shall require modification of a proposed final site plan if zoning ordinance amendments, effective after the date of preliminary site plan approval but before final site plan approval, require changes that do not affect the location and dimensions of the buildings and related structures on the site. 3. An approved preliminary site plan shall be valid for a period of five (5) years, provided that the developer: (a) Submits a final site plan within three (3) years of such approval, and (b) Thereafter diligently pursues approval of the final site plan. Diligent pursuant shall have the same meaning as in section 70-25(f) of the City Code. C. Authorization of site development under final site plans approved before change in zoning ordinance; lapsing and extension of final site plans. 1. Where the development of a site requires the approval of a site plan by the city, any final site plan which was lawfully approved before the effective date of this ordinance or before any applicable amendment to this ordinance shall be valid for a period of not less than five (5) years from the date of approval. During the time that the final site plan is valid, no change or amendment to this ordinance or any other applicable city ordinance or regulation adopted after the date of final site plan approval shall adversely affect the right of the developer or the developer's successor in interest to commence and complete an approved development in accordance with the lawful terms of the final site plan, unless the change or amendment is required to comply with state law or there has been a mistake, fraud or a change in circumstances substantially affecting the public health, safety or welfare. 2. At the end of the five-year period, an approved final site plan shall automatically lapse and become void, unless the director of development and permits, or designee, upon application filed by the developer or successor prior to the date of lapse, approves an extension of the approval period. No extension shall be granted for any plan that would violate local, state or federal law, regulations, mandatory department of transportation engineering and safety requirements, and other mandatory engineering and safety requirements. In the event of the lapse of an approved final site plan, application for a new preliminary site plan shall be required, under the provisions of the zoning ordinance and other applicable law existing at the time of the new application. D. Effect of certain laws on preliminary and final site plans. As provided for in section 15.2-2261.E., Code of Virginia, 1950, as amended, nothing in subsections (B) and (C) above shall be construed to affect the application of the following to both preliminary and final site plans: 1. The application, to the greatest extent possible, to individual lots within site plans, of the provisions of the city's ordinances implementing the Chesapeake Bay Preservation Act. 2. The application to individual lots within site plans of the provisions of the city's ordinances enacted to comply with the requirements of the Federal Clean Water Act, section 402(p.) of the stormwater program and regulations promulgated thereunder by the Environmental Protection Agency. 3. The authority of city council to impose valid conditions upon approval of any conditional use permit. E. Authorization of a use or structure under conditional use permits. 1. Where a conditional use permit has been issued to permit a particular use on a site before the effective date of this zoning ordinance or before the date of any applicable amendment to this ordinance, the permit shall be deemed to authorize the conditional use granted, unless the permit expires. 2. At the time that a site plan approval or building permit issuance is sought for the development of the site under the use permit, the layout and construction of the site shall comply with the zoning ordinance in effect at that time, as provided for in subsection (B) above, unless the conditional use permit included a specific site plan that was approved as part of the use permit. 3. Where a specific site plan with specified dimensions that comply with this zoning ordinance then in effect has been approved as part of the conditional use permit, construction in accordance with the terms of the approved plan shall be deemed to be authorized. Any new zoning ordinance requirements that become effective after the date the conditional use permit is approved shall still apply to all construction on the site, provided that they do not affect the location and dimensions of the buildings and related structures as approved in the site plan accompanying the use permit. All site plans approved in conjunction with a conditional use permit shall be considered preliminary site plans. 4. With the exception of churches, where the use conducted on a site was established at a time when such use was a permitted use on the site under the zoning ordinance and subsequent amendment of the zoning ordinance changes such use to a conditional use of that site, no extension or expansion of that use, building or structure may occur unless a conditional use permit is obtained for both the existing use and the proposed expansion or extension. Denial of a use permit application under this subsection shall not affect the continued status of the existing use as a lawful nonconforming use. 5. Lawfully nonconforming churches existing in those zoning districts in which churches are now a conditional use, other than the B-5 district, may be expanded in accordance with section 17-111 of this ordinance, except that signage must conform with the requirements of the zoning district in which the property is located. Lawfully nonconforming churches in the B-5 district may only be expanded with a conditional use permit. 6. If a conditional use permit granted by city council is allowed to lapse or otherwise becomes void, any subsequent application for a use permit for the site shall comply with the requirements of the zoning ordinance in effect when the application for the new use permit is approved.
(Ord. No. 98-O-012, 1-20-98; Ord. No. 01-O-032, 4-17-01; Ord. No. 06-O-023, 2-21-06; Ord. No. 09-O-007, 1-27-09; Ord. No. 09-O-051, 5-19-09; Ord. No. 24-O-090, 8-20-24; Ord. No. 25-O-107, 10-21-25)