Sec. 2-336. - Same—Change orders and modifications.
Contracts for construction may include provisions for modification during performance, but no contract may be increased by more than twenty-five (25) percent of the amount of the contract or thirty thousand dollars ($30,000.00), whichever is greater, without the advance written approval of the appropriate governing body.
(Ord. No. 1015, 6-26-91; Ord. No. 1144, 7-5-95; Ord. No. 09-0005, 4-29-09)