Sec. 33.1-10. - Modifications and change orders.
A public contract may include provisions for modifications and change orders during performance, except that no contract may be increased by more than five thousand dollars ($5,000.00) without the written approval of the city manager. Such modifications and change orders shall not be artificially divided to avoid this procedure.
(Ord. No. 33,095, § 1, 9-11-84)