Sec. 12-182. - Progress payments, retainage, and penalty on construction contracts.

(a) In any contract for construction which provides for progress payments in installments based upon an estimated percentage of completion, the contractor shall be paid at least 95 percent of the earned sum when payment is due, with not more than five percent being retained to assure faithful performance of the contract. All amounts withheld may be included in the final payment. (b) Any subcontract for a public project which provides for similar progress payments shall be subject to the same limitations. (c) Any contract for the sum of $200,000.00 or more for construction of highways, roads, streets, bridges, parking lots, demolition, clearing, grading, excavating, paving, pile driving, miscellaneous drainage structures, and the installation of water, gas, sewer lines and pumping stations where portions of the contract price are to be retained shall include in the bid proposal an option for the contractor to use an escrow account procedure as set out in Code of Virginia, § 2.2-4334, for utilization of the retainage funds by so indicating in the bid documents. In the event the contractor elects to use the escrow account procedure, the escrow agreement form included in the bid documents and contract shall be executed and submitted to the city within 15 calendar days after notification of award of the contract. If the escrow agreement form is not submitted within the 15-day period, the contractor shall forfeit his rights to use the escrow account procedure. (d) In any contract for construction with the city which includes a payment of interest on retained funds, the city may require a provision whereby the contractor, exclusive of reasonable circumstances beyond the control of the contractor, as determined by the purchasing administrator and stated in the contract, shall pay a specified penalty for each day exceeding the completion date stated in the contract.

(Code 1988, § 12-182; Ord. No. 1995-77, § 1, 6-27-1995; Ord. No. 2002-22, §§ 1, 3, 5-14-2002)

Ask a question about Portsmouth law

Corpus searches the Portsmouth sections it holds and shows the ones that match, with their citations. Free, no sign-in.