§ 11.10.100 — Construction in right-of-way

Federal Way Revised Code (The Federal Way Revised Code is current through Ordinance 26-1052, passed September 1, 2026.) · Federal Way Revised Code § 11.10.100

Corpus is an independent public-information project, not the official City of Federal Way website. Stable reference: corpuslaw.us/code/7c3d88bd-f125-44d4-aee7-a0b95d7a3815

11.10.100 Construction in right-of-way.

(1) Right-of-way permit. A franchisee shall submit an application for, pay the permit fee, and obtain a right-of-way permit to perform work in any public rights-of-way. No work, other than emergency repairs, shall commence without such a permit. Emergency repairs may be made immediately with notification given to the city no later than the next business day. (2) Installation. In accordance with the permit issued, all transmission lines, equipment, and structures shall be located and installed so as to cause minimum interference with the rights and reasonable convenience of property owners, and at all times shall be maintained in a safe condition, and in good order and repair. Suitable barricades, flags, lights, flares, or other devices shall be used at such times and places as are reasonably required for the safety of the public. Any poles or other fixtures placed in any street by a franchisee shall be placed in such manner as not to interfere with the usual travel on such public way. (3) Interference with use of streets. When installing, locating, laying, or maintaining cable facilities, apparatus, or improvements, a franchisee shall not interfere with the use of any street to any greater extent than is necessary, and shall leave the surface of any such street in as good condition as it was prior to performance by franchisee of such work. Any facility, apparatus, or improvement under this chapter shall be laid, installed, located, or maintained in conformance with instructions given by, and to the satisfaction of the city. In any event, a franchisee shall, at its own expense, and to the satisfaction of the city in accordance with the terms of the right-of-way permit, restore to city standards and specifications any damage or disturbance caused to streets as a result of franchisee’s construction or operations. (4) Relocation/removal. Upon receipt of 90 days’ prior written notice, a franchisee, at its own expense, and within the time period prescribed by the city, shall protect, support, temporarily disconnect, relocate, or remove any of its cable facilities or property when, in the judgement of the city, the same is required by reason of traffic conditions, public safety, improvements by governmental agencies and/or any other city use of the franchise area. Nothing herein shall be deemed a taking of the property of a franchisee, and franchisee shall be entitled to no surcharge by reason of this section. (5) City’s performance of work. After receipt of 30 days’ prior written notice, and upon the failure of a franchisee to commence, pursue, or complete any work required by the provisions of this chapter or failure to comply with any applicable federal, state or city laws, ordinances, rules, regulations or standards to be performed on any street, within the reasonable time prescribed and to the satisfaction of the city, the city may, at its option, cause such work to be done, and a franchisee shall pay to the city the reasonable cost thereof which costs may include the city’s reasonable overhead and administrative expense, within 30 days after receipt of demand.

(Ord. No. 95-239, § 10, 8-1-95. Code 2001 § 9-710.)