§ 18.30.010 — Application and review process

Federal Way Revised Code (The Federal Way Revised Code is current through Ordinance 26-1052, passed September 1, 2026.) · Federal Way Revised Code § 18.30.010

Corpus is an independent public-information project, not the official City of Federal Way website. Stable reference: corpuslaw.us/code/2bc5c3ec-8d76-474b-ba56-5ba42d70cba6

18.30.010 Application and review process.

The general procedure for processing an application for a short subdivision consists of the following steps: (1) An optional preapplication conference between the proponent and city staff to discuss land use, site design, transportation, and environmental issues. (2) Review of the short subdivision application to determine whether or not the application is complete and acceptable for filing. (3) Review of the application by the department of community development, Lakehaven utility district, city of Tacoma public works department, and county department of public health, if septic systems are to be utilized. (4) Approval, approval with conditions, or denial of the short subdivision by the director of the department of community development. (5) Review of engineering drawings for required public improvements. (6) Approval of engineering plans by the director. (7) Substantial completion of required improvements. (8) Recording of short subdivision in the office of the county division of elections and records.

(Ord. No. 26-1044, § 29, 6-16-26; Ord. No. 07-554, § 5(Exh. A(2)), 5-15-07; Ord. No. 97-291, § 3, 4-1-97; Ord. No. 90-41, § 1(16.130.10 – 16.130.70), 2-27-90. Code 2001 § 20-81.)