For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 10.36.260 — Backfilling – Compaction

Spokane Municipal Code; partial · SMC 10.36.260 · Effective

Corpus is an independent public-information project, not the official City of Spokane website. Stable reference: corpuslaw.us/code/4bd8925b-d9ce-429b-a0a9-9e454964d46d

Section 10.36.260 Backfilling – Compaction

The excavator must compact backfill to a degree equivalent to the original undisturbed ground in which the trench was dug. The excavator may select, based upon the character of the soil, to compact by mechanical tampers or vibrators, by rolling in layers, or by water settling, except that water settling requires the approval of the director of engineering services.

Date Passed: Monday, June 4, 2007 Effective Date: Wednesday, July 11, 2007 ORD C34041 Section 1 (Recodification)

Ask a question about Spokane law

Corpus searches the Spokane sections it holds and shows the ones that match, with their citations. Free, no sign-in.