§ 13.16.030 — Concurrency test
Municipal Code, City of Tacoma, Washington (Tacoma Municipal Code current through legislation adopted 2026-09-30 (eCode360 publication TA6977, scraped 2026-11-18)) · Tacoma Municipal Code § 13.16.030
Corpus is an independent public-information project, not the official City of Tacoma website. Stable reference: corpuslaw.us/code/95be34ab-fcc6-4b5e-8cce-5ea54e2885dd
§ 13.16.030: Concurrency test.
A. Application. All development permit applications are subject to a concurrency test except those exempted in Section 13.16.050. If a concurrency test is conducted for the preliminary plat application, no concurrency test shall be required for the final plat application. B. Procedures. The concurrency test will be performed in the processing of the development permit and conducted by Planning and Development Services and the facility and service providers. 1. Planning and Development Services shall provide the overall coordination of the concurrency test by notifying the facility and service providers of all applications requiring a concurrency test as set forth in subsection A above; notifying the facility and service providers of all exempted applications which use capacity as set forth in Section 13.16.050; notifying the applicant of the test results; notifying the facility and service providers of the final outcome (approval or denial) of the development permit; and notifying the facility and service providers of any expired development permits or discontinued certificates of capacity. 2. All facility and service providers shall be responsible for maintaining and monitoring their available and planned capacity by conducting the concurrency test, for their individual facility, for all applications requiring a concurrency test as set forth in subsection A above; reserving the capacity needed for each application; accounting for the capacity for each exempted application which uses capacity as set forth in Section 13.16.050; notifying Planning and Development Services of the results of the tests; and reinstating any capacity for an expired development permit, discontinued certificate of capacity, or other action resulting in an applicant no longer needing capacity which has been reserved. 3. The facility and service providers shall be responsible for annually reporting to the City of Tacoma the total, available and planned capacity of their facility or service as of the end of each calendar year. Such reporting shall be made before January 31st for inclusion in the amendment process of the Capital Facilities Program. C. Test. Development applications that would result in a reduction of a level of service below the minimum level of service standard cannot be approved. For potable water, electric utilities, sanitary sewer, solid waste and storm water management only available capacity will be used in conducting the concurrency test. For roads, transit, law enforcement, fire, emergency medical service, schools, parks and libraries, available and planned capacity will be used in conducting the concurrency test. 1. If the capacity of concurrency facilities is equal to or greater than the capacity required to maintain the level of service standard for the impact from the development application, the concurrency test is passed. A certificate of capacity will be issued according to the provisions of Section 13.16.040. 2. If the capacity of concurrency facilities is less than the capacity required to maintain the level of service standard for the impact from the development application, the concurrency test is not passed. The applicant may: a. Accept 90-day reservation of concurrency facilities that exist and modify the application to reduce the need for concurrency facilities that do not exist; b. Accept 90-day reservation of concurrency facilities that exist and demonstrate to the service provider’s satisfaction that the development will have a lower need for capacity than usual and, therefore, capacity is adequate; c. Accept 90-day reservation of concurrency facilities that exist and arrange with the service provider for the provision of the additional capacity of concurrency facilities required; or d. Appeal the results of the concurrency test to the Hearing Examiner in accordance with the provisions of 13.16.070. D. Concurrency inquiry application. An applicant may inquire whether or not concurrency facilities exist without an accompanying request for a development permit. As set forth in Tacoma Municipal Code Chapter 2.09, Fee Code, a fee may be charged for such concurrency test. Any available capacity cannot be reserved. A certificate of capacity will only be issued in conjunction with a development permit approval as outlined in 13.16.040.
( Ord. 25646 § 3, 1994-12-13 ; Ord. 27893 Ex. A, 2010-06-15 ; Ord. 28109 Ex. O, 2012-12-04 )
Ask a question about Tacoma law
Corpus searches the Tacoma sections it holds and shows the ones that match, with their citations. Free, no sign-in.